Queen Palace
Deedo IDDP-THN-SNH4Completion was pushed back 4 months, to Sep 2027; no MahaRERA orders on record.
Dombivli, Thane 421202 · Promoter: Nandkusum Infra LLP
Completion was pushed back 4 months, to Sep 2027
- This projectRegistered 5 Jun 2024, completion promised 30 May 2027, revised to 30 Sep 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700056476
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700056476 | 5 Jun 2024 | 30 May 2027 | 30 Sep 2027 | Nandkusum Infra LLP | Project page |
Documents70
1 document held by Deedo, 69 filings listed on MahaRERA's project page
Finance
Legal
Show all 70 documentsShow fewer documents
Migrated
- 2 a Details of encumbrances concerned to FinanceNO LEGAL LITIGATION ENCUMBRANCES.pdf · uploaded 26 Mar 2024Source
- 1 b Details of encumbrances concerned to LegalNO FINANCE ENCUMBRANCES.pdf · uploaded 26 Mar 2024Source
- 2 b Details of encumbrances concerned to LegalNO LEGAL LITIGATION ENCUMBRANCES.pdf · uploaded 26 Mar 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentKDMC COMMENCEMENT CERTFICATE NANDUSUM LLP_compressed.pdf · uploaded 26 Mar 2024Source
- 1 Declaration about Commencement CertificateDECLERATION ABOUT COMMENCMENT CERTIFICATE.pdf · uploaded 26 Mar 2024Source
- 1 Declaration in FORM BAFFIDAVIT CUM DECLERATION UJALA BHOIR.pdf · uploaded 26 Mar 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE PYARELAL BHOIR.pdf · uploaded 26 Mar 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE UJALA BHOIR.pdf · uploaded 26 Mar 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE URVASU BHOIR.pdf · uploaded 26 Mar 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE VRUSHABH BHOIR.pdf · uploaded 26 Mar 2024Source
- 1 Proforma of Agreement for salesale draft.pdf · uploaded 26 Mar 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT a.pdf · uploaded 26 Mar 2024Source
- 1 Deviation Report with respect to Allotment letterNO ANY DEVIATION WITH RESPECT TO ALLOTTMENT LETTER.pdf · uploaded 26 Mar 2024Source
- 1 Deviation Report with respect to model copy of AgreementSELF DECLERATION REGARDING PROFORMA AGREEMENT FOR SALE.pdf · uploaded 26 Mar 2024Source
- 1 CERSAI detailscersai search report.pdf · uploaded 28 Mar 2024Source
- 1 Proforma of Allotment letterALLOTMENT LETTER- queen.pdf · uploaded 28 Mar 2024Source
- 1 Copy of Layout Approval (in case of layout)sanction plan 2.pdf · uploaded 10 Apr 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentsanction plan 2.pdf · uploaded 10 Apr 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERIFICATE SCAN D.pdf · uploaded 11 Apr 2024Source
- 1 Other – LegalDECLARATION CUM UNDER.pdf · uploaded 10 May 2024Source
- 1 Other – TechnicalDECLARATION CUM UNDER.pdf · uploaded 10 May 2024Source
- 2 Other – Legalkdmc.pdf · uploaded 27 May 2024Source
- 1 Other – Financekdmc.pdf · uploaded 27 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)R K ASSOCIATES FORM 1 APR TO JUNE 2024_compressed.pdf · uploaded 31 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)R K ASSOCIATES FORM 1 JULY TO SEP 2024_compressed.pdf · uploaded 31 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 APR TO JUNE 2024.pdf · uploaded 31 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 JULY TO SEP 2024.pdf · uploaded 31 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)MANOHAR PATIL FORM 2 APR TO JUNE 2024_compressed.pdf · uploaded 31 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)MANOHAR PATIL FORM 2 JULY TO SEP 2024_compressed.pdf · uploaded 31 Oct 2024Source
- Form 32 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 20 May 2025Source
- Form 32 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 20 May 2025Source
- Form 13 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 20 May 2025Source
- Form 2Form 2 · uploaded 20 May 2025Source
- Form 12 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 20 May 2025Source
- Form 2form 1 oct-dec 24.pdf · uploaded 20 May 2025Source
- Form 3form 2 oct-dec 24.pdf · uploaded 20 May 2025Source
- Self-declaration of Quarterly Progressform 3 oct-dec 24.pdf · uploaded 20 May 2025Source
- Form 1form 2 oct-dec 24.pdf · uploaded 20 May 2025Source
- Form 2form 3 oct-dec 24.pdf · uploaded 20 May 2025Source
- Form 32 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf · uploaded 20 May 2025Source
- Self-declaration of Quarterly Progressform 1 oct-dec 24.pdf · uploaded 20 May 2025Source
- Form 1Form 1 nandkusum llp apr to June 2025 PDF.pdf · uploaded 30 Oct 2025Source
- Form 2Form 2 nandkusum llp apr to June 2025.pdf · uploaded 30 Oct 2025Source
- Form 3Form 3 Nandkusum infra llp April to June 2025 PDF_compressed.pdf · uploaded 30 Oct 2025Source
- Disclosure of Sold and Booked Inventorynandkusum infra q1 30-6-25.pdf · uploaded 30 Oct 2025Source
- Form 1Form 1 nandkusum llp july to sep 2025 PDF.pdf · uploaded 30 Oct 2025Source
- Form 2Form 2 nandkusum llp july to sep 2025 PDF.pdf · uploaded 30 Oct 2025Source
- Form 3Form 3 Nandkusum infra llp july to sep 2025 PDF_compressed.pdf · uploaded 30 Oct 2025Source
- Disclosure of Sold and Booked Inventorynandkusum infra q2 30-9-25.pdf · uploaded 30 Oct 2025Source
- Form 1form 1 oct-dec.pdf · uploaded 5 May 2026Source
- Form 2form 2 oct-dec.pdf · uploaded 5 May 2026Source
- Form 3form 3 oct-dec.pdf · uploaded 5 May 2026Source
- Disclosure of Sold and Booked Inventoryform 3 oct-dec.pdf · uploaded 5 May 2026Source
- Form 1form 1 jan-march.pdf · uploaded 5 May 2026Source
- Form 2form 2 jan-march.pdf · uploaded 5 May 2026Source
- Form 3form 3 jan-march.pdf · uploaded 5 May 2026Source
- Disclosure of Sold and Booked Inventoryform 3 jan-march.pdf · uploaded 5 May 2026Source
Technical
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals12, SURVEY NO 35 NEW SURVEY NO 129 OLD HISSA NO 1
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Village
- Dombivli
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | R K Associates | — |
| Chartered accountant | Monica Vikas Kulkarni | — |
| Engineer | Rcc Engineers | — |
Source: MahaRERA project page. Contact details are not shown.