Deedo IDDP-THN-C6C8Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 44% of its units are booked.
Dombivli, Thane 421201 · Promoter: Omkar Shashikant Dahotre
Its promised completion date, Jun 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 15 Dec 2022, completion promised 30 Jun 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700048193
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700048193 | 15 Dec 2022 | 30 Jun 2025 | 30 Jun 2025 | Omkar Shashikant Dahotre | Project page |
Documents66
1 document held by Deedo, 65 filings listed on MahaRERA's project page
Finance
- PAN CardOMKAR - PAN.pdf · uploaded 30 Jun 2022Source
Legal
Migrated
- 1 PAN CardOMKAR - PAN.pdf · uploaded 30 Jun 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrance_Certificate_.pdf · uploaded 30 Jun 2022Source
- 1 Copy of Layout Approval (in case of layout)11 Plan Copy.pdf · uploaded 30 Jun 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan Copy.pdf · uploaded 30 Jun 2022Source
Show all 66 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certifiacte_compressed.pdf · uploaded 30 Jun 2022Source
- 1 Declaration about Commencement CertificateCertificate_CC.pdf · uploaded 30 Jun 2022Source
- 1 Declaration in FORM BForm_B_Mr Omkar_Dahotre_compressed.pdf · uploaded 30 Jun 2022Source
- 1 CERSAI detailsCERSAI DETAILS.pdf · uploaded 30 Jun 2022Source
- 1 a Details of encumbrances concerned to Finance3 Cersai Encumbrance Certificate.pdf · uploaded 1 Jul 2022Source
- 1 Proforma of Allotment letter4 Allotment Letter Format.pdf · uploaded 4 Jul 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Letter.pdf · uploaded 4 Jul 2022Source
- 1 Deviation Report with respect to Allotment letter14 Deviations_Certificate_Allotment_Letter_.pdf · uploaded 4 Jul 2022Source
- 2 Copy of Layout Approval (in case of layout)15 Plan copy A.pdf · uploaded 4 Sep 2022Source
- 2 Building Plan Approval / NA Order for plotted development15 Plan copy A.pdf · uploaded 4 Sep 2022Source
- 1 Copy of the legal title report16 Title report_compressed.pdf · uploaded 6 Sep 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)17 Form -3 Certificate.pdf · uploaded 6 Sep 2022Source
- 3 Building Plan Approval / NA Order for plotted development17 Form -3 Certificate.pdf · uploaded 7 Sep 2022Source
- 1 Proforma of Agreement for sale22 Agreement.pdf · uploaded 22 Oct 2022Source
- 1 Deviation Report with respect to model copy of Agreement21 Deviations_Agreement__compressed.pdf · uploaded 22 Oct 2022Source
- 1 Other – TechnicalConfirmation from KDMC.pdf · uploaded 7 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01 Architect Certificate.pdf · uploaded 9 Jun 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02 Engineer Certificate.pdf · uploaded 9 Jun 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentPlan Copy- 1.pdf · uploaded 21 Oct 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentPlan Copy- 2.pdf · uploaded 21 Oct 2023Source
- 6 Building Plan Approval / NA Order for plotted developmentPlan Copy- 3.pdf · uploaded 21 Oct 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentComencement Certificate - revised.pdf · uploaded 21 Oct 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)(Q1) Form 01 - Architect's Certificate.pdf · uploaded 25 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)(Q2) Form 1.pdf · uploaded 25 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architecture Certificate Signed.pdf · uploaded 25 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 Architecture Certificate Signed.pdf · uploaded 25 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)(Q1) Form 02 - Engineer's Certificate.pdf · uploaded 25 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)(Q2) Form 02.pdf · uploaded 25 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engg Certificate 31-12-2023.pdf · uploaded 25 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)(Q4) Signed Form - 03_compressed.pdf · uploaded 25 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)(Q1) Form - 03_compressed.pdf · uploaded 25 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2023_compressed.pdf · uploaded 25 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2023_compressed.pdf · uploaded 25 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5_Paramount_22-23.pdf · uploaded 23 Feb 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 Signed.pdf · uploaded 28 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 Signed.pdf · uploaded 28 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4 Signed_Compressed.pdf · uploaded 28 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 Signed_Compressed.pdf · uploaded 28 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q4 Signed.pdf · uploaded 28 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate Signed.pdf · uploaded 28 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Paramount Form 5 Signed.pdf · uploaded 14 Nov 2024Source
- 1 Other – TechnicalFORM-4.pdf · uploaded 12 May 2025Source
Technical
- Document11 Plan Copy.pdf · uploaded 30 Jun 2022Source
- DocumentPlan Copy.pdf · uploaded 30 Jun 2022Source
- Document15 Plan copy A.pdf · uploaded 4 Sep 2022Source
- Document15 Plan copy A.pdf · uploaded 4 Sep 2022Source
- Document17 Form -3 Certificate.pdf · uploaded 7 Sep 2022Source
- Other – TechnicalConfirmation from KDMC.pdf · uploaded 7 Dec 2022Source
- DocumentPlan Copy- 1.pdf · uploaded 21 Oct 2023Source
- DocumentPlan Copy- 2.pdf · uploaded 21 Oct 2023Source
- DocumentPlan Copy- 3.pdf · uploaded 21 Oct 2023Source
- Other – TechnicalFORM-4.pdf · uploaded 12 May 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsCTS No.6864 to 6867
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, 3BHK9 units in all
- Address
- CTS No.6864 to 6867, Situated at Navagaon Village, ThakurliPIN 421201
- Village
- Dombivli, Kalyan taluka
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Nehru Maidan Jain Mandir
- South
- RBT School
- East
- Maitri Indira Sadan
- West
- Dev Mangal Apartment
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking9 units
4 of 9 units booked (44%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 64.89 sq m · 698 sq ft | 6 | 3 |
| 3BHK | 81.53 sq m · 878 sq ft | 3 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ankur A Shetye | — |
| Chartered accountant | Ca Sagar Joshi | — |
| Engineer | Gopal M Bennur | — |
Source: MahaRERA project page. Contact details are not shown.