Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 48% of its units are booked.

Dombivli, Thane 421201 · Promoter: M/s Riddhi Siddhi Infraprojects

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales48% booked10 of 21 units · as the promoter reported to MahaRERA
Mahek Meadows project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 14 Nov 2024, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700077954
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170007795414 Nov 202431 Dec 202630 Apr 2027M/s Riddhi Siddhi InfraprojectsProject page
Documents75

1 document held by Deedo, 74 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card Riddhi Siddhi Infraprojects.pdf · uploaded 4 Jul 2024Source
  • Other – FinanceClarification Letter Signed.pdf · uploaded 12 Nov 2024Source

Legal

  • Declaration Form BCompany Form - B_compressed.pdf · uploaded 4 Jul 2024Source
  • Legal Title reportLegal Title Report.pdf · uploaded 4 Jul 2024Source
  • Other – LegalAnnexure -A.pdf · uploaded 8 Oct 2024Source

Migrated

  • 1 PAN CardPan Card Riddhi Siddhi Infraprojects.pdf · uploaded 4 Jul 2024Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 4 Jul 2024Source
Show all 75 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceCertificate of Encumbrances- Signed.pdf · uploaded 4 Jul 2024Source
  • 1 Declaration in FORM BCompany Form - B_compressed.pdf · uploaded 4 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form2 Signed.pdf · uploaded 4 Jul 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certitificate.pdf · uploaded 4 Jul 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan Sanction Copy (1).pdf · uploaded 4 Jul 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan Sanction Copy (2).pdf · uploaded 4 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan Sanction Copy (3).pdf · uploaded 4 Jul 2024Source
  • 1 Declaration about Commencement CertificateDeclaration certificate of CC- Signed.pdf · uploaded 4 Jul 2024Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 4 Jul 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Letter Allotment Letter -Signed.pdf · uploaded 4 Jul 2024Source
  • 1 b Details of encumbrances concerned to LegalCertificate of Encumbrances- Signed.pdf · uploaded 4 Jul 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Letter (Sale Agreement) Signed.pdf · uploaded 4 Jul 2024Source
  • 1 Proforma of Agreement for saleDraft Agreement - Upload (1).pdf · uploaded 4 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Partners Details Santosh Bhanushali Signed.pdf · uploaded 4 Jul 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Partners Details Sudesh Chudnaik.pdf · uploaded 4 Jul 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Partners Details Darshan Dhuker.pdf · uploaded 4 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1 Signed.pdf · uploaded 8 Oct 2024Source
  • 1 Other – LegalAnnexure -A.pdf · uploaded 8 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 8 Oct 2024Source
  • 1 Other – TechnicalKDMC mail verification.pdf · uploaded 8 Oct 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B bank.pdf · uploaded 8 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclousre of Loan.pdf · uploaded 8 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Site Plan.pdf · uploaded 17 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form_3_Riddhi_Siddhi_Infraprojects.pdf · uploaded 17 Oct 2024Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 24 Oct 2024Source
  • 1 Other – FinanceClarification Letter Signed.pdf · uploaded 12 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01 Architect Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Signed 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02 Engg Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 01 Architect Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Signed 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02 Engg Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)riddhi_siddhi_from_3_march-2025.pdf · uploaded 1 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RIDHI SIDHI-Q4-FORM 1.pdf · uploaded 2 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)RIDHI SIDHI-Q4-FORM 2.pdf · uploaded 2 May 2025Source
  • Withdrawal Update Form 1Riddhi_siddhi_form-1.pdf · uploaded 15 Jul 2025Source
  • Withdrawal Update Form 2Riddhi_Siddhi_form-2.pdf · uploaded 15 Jul 2025Source
  • Withdrawal Update Form 3Riddhi_Siddhi_Form_3 Signed.pdf · uploaded 15 Jul 2025Source
  • Withdrawal Update Form 1Riddhi_siddhi_form-1.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 2Riddhi_Siddhi_form-2.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 3Riddhi_Siddhi_Form_3 Signed.pdf · uploaded 21 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 Signed.pdf · uploaded 4 Oct 2025Source
  • Withdrawal Update Form 1riddhi siddhi Form 1 Q2 Fy 2025-26.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 2Riddi Siddhi Form 2 Q2 Fy 2025-26.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 3Form_-3_Riddhi_Siddhi.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 1Form 1 RSI Q3.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 2Form 2 RSI Q3.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 RSI Q3.pdf · uploaded 27 Feb 2026Source
  • Withdrawal Update Form 1Form 1 RSI Q4.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 2Form 2 RSI Q4.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 3Form 3 RSI Q4.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 1Form-1 Q1 26-27.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 2Form-2 Q1 26-27.pdf · uploaded 24 Jul 2026Source
  • Withdrawal Update Form 3Form 3 Q1 26-27.pdf · uploaded 24 Jul 2026Source

Technical

  • DocumentPlan Sanction Copy (3).pdf · uploaded 4 Jul 2024Source
  • DocumentPlan Sanction Copy (2).pdf · uploaded 4 Jul 2024Source
  • DocumentPlan Sanction Copy (1).pdf · uploaded 4 Jul 2024Source
  • Other – TechnicalKDMC mail verification.pdf · uploaded 8 Oct 2024Source
  • DocumentSite Plan.pdf · uploaded 17 Oct 2024Source

Technical (Architect)

  • DocumentForm 01 Architect Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • DocumentForm 01 Architect Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • DocumentRIDHI SIDHI-Q4-FORM 1.pdf · uploaded 2 May 2025Source
  • DocumentForm-1 Q1 26-27.pdf · uploaded 24 Jul 2026Source

Technical (Engineer)

  • DocumentForm 02 Engg Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • DocumentForm 02 Engg Certificate 31-12-2024.pdf · uploaded 23 Jan 2025Source
  • DocumentRIDHI SIDHI-Q4-FORM 2.pdf · uploaded 2 May 2025Source
  • DocumentForm-2 Q1 26-27.pdf · uploaded 24 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsGau. Plot No.46, Survey No.84/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1 BHK Society Member, 1RK, 2 BHK Society Member, 3 BHK Society Member21 units in all
Address
Survey No.84/2, Gau. Plot No.46, Survey No. 84/2, Gau. No.46PIN 421201
Village
Dombivli, Kalyan taluka
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

Gau. Plot No.46Survey No.84/2

Boundaries

North
6 mtr road
South
Naala
East
Property of Shiv Shraddha CHS
West
Property of New Sadhana CHS

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking21 units

10 of 21 units booked (48%), as the promoter reported to MahaRERA

1BHK · 8 units1 BHK Society Member · 5 units1RK · 1 unit2 BHK Society Member · 6 units3 BHK Society Member · 1 unit
TypeCarpet areaUnitsBooked
1BHK33.57 sq m · 361 sq ft50
1BHK34.2 sq m · 368 sq ft30
1 BHK Society Member33.57 sq m · 361 sq ft11
1 BHK Society Member34.2 sq m · 368 sq ft31
1 BHK Society Member35.04 sq m · 377 sq ft11
1RK24.4 sq m · 263 sq ft10
2 BHK Society Member47.07 sq m · 507 sq ft11
2 BHK Society Member47.91 sq m · 516 sq ft55
3 BHK Society Member56.91 sq m · 613 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKeshav Chikodi—
Chartered accountantCa Sagar Joshi—
Chartered accountantHarshal Jain—
EngineerMadhav B Chikodi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology