Deedo IDDP-THN-RD6HCompletion was pushed back 4 months, to Jul 2030; no MahaRERA orders on record; 0% of its units are booked.
Chikanghar, Thane 421301 · by Desire Realty
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2030
- This projectRegistered 16 Jul 2025, completion promised 31 Mar 2030, revised to 31 Jul 2030.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700080843
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700080843 | 16 Jul 2025 | 31 Mar 2030 | 31 Jul 2030 | Desire Realty | Project page |
Documents55
1 document held by Deedo, 54 filings listed on MahaRERA's project page
Show all 55 documentsShow fewer documents
Migrated
- 1 a Details of encumbrances concerned to FinanceNON ENCB.pdf · uploaded 12 Mar 2025Source
- 1 Copy of Layout Approval (in case of layout)ORION CC PLAN.pdf · uploaded 12 Mar 2025Source
- 1 Proforma of Allotment letterDESIRE AL.pdf · uploaded 12 Mar 2025Source
- 1 Declaration in FORM BDESIRE BFORM.pdf · uploaded 12 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)DESIRE FORM1.pdf · uploaded 12 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)DESIRE FORM3.pdf · uploaded 12 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)DESIREFORM2.pdf · uploaded 12 Mar 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentORION CC.pdf · uploaded 12 Mar 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentORION CC PLAN.pdf · uploaded 12 Mar 2025Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 12 Mar 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)DESIRE FORMATA.pdf · uploaded 12 Mar 2025Source
- 1 Deviation Report with respect to Allotment letterAL DEV.pdf · uploaded 12 Mar 2025Source
- 1 b Details of encumbrances concerned to LegalNON ENCB.pdf · uploaded 12 Mar 2025Source
- 1 Deviation Report with respect to model copy of AgreementAFS DEV.pdf · uploaded 12 Mar 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTREST ALL PARTNERS.pdf · uploaded 12 Mar 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)DESIRE FORMATB.pdf · uploaded 12 Mar 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDESIRE CF DISCLOSURE.pdf · uploaded 12 Mar 2025Source
- 1 Copy of the legal title reportDESIRE TITLE.pdf · uploaded 15 Apr 2025Source
- 1 Declaration about Commencement CertificateORION CC DEC.pdf · uploaded 24 Apr 2025Source
- 1 Other – FinanceRB DECLARATION.pdf · uploaded 24 Apr 2025Source
- 1 Other – TechnicalORION DECLARATION.pdf · uploaded 24 Apr 2025Source
- 1 Proforma of Agreement for saleORION AFS.pdf · uploaded 24 Apr 2025Source
- 2 Other – FinanceDESIRE REALTY-compressed.pdf · uploaded 20 Jun 2025Source
- 3 Other – FinanceRB AND BHOIRR DEC.pdf · uploaded 7 Jul 2025Source
- Withdrawal Update Form 1Oriion Form 1 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1Oriion Form 1 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1Orion Form 1 31DEC25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1Oriion Form 1 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1Oriion Form 1 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Orion Form 2 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Orion Form 2 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Orion Form 2 31DEC25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Orion Form 2 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 2Orion Form 2 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3ORION Form 3 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3ORION Form 3 30SEP25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3ORION Form 3 31DEC25.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3ORION Form 3 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 3ORION Form 3 31MAR26.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1ORION FORM1 30JUN26.pdf · uploaded 3 Sep 2026Source
- Withdrawal Update Form 2ORION FORM2 30JUN26.pdf · uploaded 3 Sep 2026Source
- Withdrawal Update Form 3ORION FORM3 30JUN26.pdf · uploaded 3 Sep 2026Source
Technical
Technical (Architect)
- DocumentORION FORM1 30JUN26.pdf · uploaded 2 Sep 2026Source
Technical (Engineer)
- DocumentORION FORM2 30JUN26.pdf · uploaded 3 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 86/1/2 86/2/A, 97/2/2
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Off banq rest kitche, Shop, 2.5BHK, 2BHK, 3BHK102 units in all
- Address
- Survey No 86/1/1, 86/1/2 86/2/A, 97/2/2, 97/2/A/1, Ram Bag Lane No.4, Kalyan WestPIN 421301
- Village
- Chikanghar, Kalyan taluka
- Location
- 19.24521, 73.13739
- Land area for this project
- 5,112 sq m (55,025 sq ft)
- Permissible built-up area
- 22,023 sq m (2,37,054 sq ft)
- Sanctioned built-up area
- 11,479 sq m (1,23,555 sq ft)
- Recreational open space
- 475 sq m (5,118 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 86/1/1, 86/1/2 86/2/A, 97/2/2, 97/2/A/1
Boundaries
- North
- 18 Mtr Road
- South
- 9 Mtr Road
- East
- 9 Mtr Road
- West
- 9 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking102 units
0 of 102 units booked (0%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | Off banq rest kitche | 806.33 sq m · 8,679 sq ft | 1 | 0 |
| Wing A | Shop | 25.36 sq m · 273 sq ft | 1 | 0 |
| Wing A | Shop | 25.86 sq m · 278 sq ft | 1 | 0 |
| Wing A | Shop | 28.94 sq m · 312 sq ft | 1 | 0 |
| Wing A | Shop | 29.49 sq m · 317 sq ft | 1 | 0 |
| Wing A | Shop | 29.84 sq m · 321 sq ft | 1 | 0 |
| Wing A | Shop | 36.88 sq m · 397 sq ft | 1 | 0 |
| Wing A | Shop | 40.63 sq m · 437 sq ft | 1 | 0 |
Show all 22 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | Shop | 94.36 sq m · 1,016 sq ft | 1 | 0 |
| Wing A | Shop | 127.25 sq m · 1,370 sq ft | 1 | 0 |
| Wing A | Shop | 181.95 sq m · 1,958 sq ft | 1 | 0 |
| Wing A | Shop | 189.19 sq m · 2,036 sq ft | 1 | 0 |
| Wing B | 2.5BHK | 62.49 sq m · 673 sq ft | 14 | 0 |
| Wing B | 2.5BHK | 65.76 sq m · 708 sq ft | 14 | 0 |
| Wing B | 2BHK | 52.78 sq m · 568 sq ft | 14 | 0 |
| Wing B | 2BHK | 52.92 sq m · 570 sq ft | 14 | 0 |
| Wing B | 3BHK | 86.42 sq m · 930 sq ft | 14 | 0 |
| Wing B | 3BHK | 86.47 sq m · 931 sq ft | 14 | 0 |
| Wing B | Shop | 27.94 sq m · 301 sq ft | 1 | 0 |
| Wing B | Shop | 29.39 sq m · 316 sq ft | 3 | 0 |
| Wing B | Shop | 32.71 sq m · 352 sq ft | 1 | 0 |
| Wing B | Shop | 38.9 sq m · 419 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | De Con Consultants | — |
| Chartered accountant | Vijaykumar Prajapati | — |
| Engineer | Associates Structure Engineers LLP | — |
| Engineer | Ganesh Patil | — |
Source: MahaRERA project page. Contact details are not shown.