It is due for completion in Jun 2027, with no extension on record; no MahaRERA orders on record; 40% of its units are booked.

Bhopar, Thane 421204 · by Mahaavir Buildcon LLP

DeliveryDue Jun 2027No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales40% booked196 of 496 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Jun 2027, with no extension on record

  • This projectRegistered 1 Dec 2020, completion promised 30 Jun 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700027307
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000273071 Dec 202030 Jun 202730 Jun 2027Mahaavir Buildcon LLPProject page
Documents154

1 document held by Deedo, 153 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD MAHAAVIR BUILDCON LLP.pdf · uploaded 21 Nov 2020Source

Legal

  • Declaration Form BAFFIDAVIT CUM DECLARATION FORM B.pdf · uploaded 21 Nov 2020Source
  • Legal Title reportTITLE CERTIFICATE.pdf · uploaded 28 Nov 2020Source
  • Legal Title reportSUPPLEMENTARY TITLE CERTIFICATE.pdf · uploaded 3 Aug 2021Source
  • OtherFORM C CONSENT FOR CORRECTION.pdf · uploaded 18 Oct 2021Source
  • OtherCONSENT FORMAT C.pdf · uploaded 21 Dec 2021Source
  • Legal Title reportTITLE CERTIFICATE 2 2023 11.pdf · uploaded 3 Nov 2023Source
Show all 154 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN CARD MAHAAVIR BUILDCON LLP.pdf · uploaded 21 Nov 2020Source
  • 1 Details of encumbrancesDEVELOPER ENCUMBRANCES CERTIFICATE.pdf · uploaded 21 Nov 2020Source
  • 1 Copy of Layout Approval (in case of layout)2020 11 09 CC PLAN SHEET 1.pdf · uploaded 21 Nov 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC PLAN SHEET 2.pdf · uploaded 21 Nov 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentCC PLAN SHEET 4.pdf · uploaded 21 Nov 2020Source
  • 1 Commencement Certificates / NA Order for plotted development2020 11 09 CC.pdf · uploaded 21 Nov 2020Source
  • 1 Declaration in FORM BAFFIDAVIT CUM DECLARATION FORM B.pdf · uploaded 21 Nov 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 21 Nov 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FORM 2.pdf · uploaded 21 Nov 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)20201123165019078.pdf · uploaded 27 Nov 2020Source
  • 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 28 Nov 2020Source
  • 1 Proforma of Allotment letterDRAFT AFS-RERA.pdf · uploaded 28 Nov 2020Source
  • 2 Details of encumbrancesCERTIFICATE OF Encumbrance.pdf · uploaded 24 Jul 2021Source
  • 2 Copy of the legal title reportSUPPLEMENTARY TITLE CERTIFICATE.pdf · uploaded 3 Aug 2021Source
  • 2 Copy of Layout Approval (in case of layout)AMENDED CC APPROVED LAYOUT PLAN S-1.pdf · uploaded 3 Aug 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED LAYOUT PLAN S-1.pdf · uploaded 4 Aug 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-2.pdf · uploaded 4 Aug 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-3.pdf · uploaded 4 Aug 2021Source
  • 6 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-4.pdf · uploaded 4 Aug 2021Source
  • 7 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-5.pdf · uploaded 4 Aug 2021Source
  • 8 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-6.pdf · uploaded 4 Aug 2021Source
  • 9 Building Plan Approval / NA Order for plotted developmentAMENDED CC APPROVED PLAN S-7.pdf · uploaded 4 Aug 2021Source
  • 2 Proforma of Allotment letterAGREEMENT FOR SALE DRAFT.pdf · uploaded 5 Aug 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentAMENDED COMMENCEMENT CERITIFICATE.pdf · uploaded 7 Aug 2021Source
  • 3 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 28 Aug 2021Source
  • 1 Declaration about Commencement CertificateDECLARATION COMMENCEMENT CERTIFICATE.pdf · uploaded 18 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE.pdf · uploaded 18 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY.pdf · uploaded 18 Oct 2021Source
  • 1 OtherFORM C CONSENT FOR CORRECTION.pdf · uploaded 18 Oct 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)download.pdf · uploaded 19 Nov 2021Source
  • 1 CERSAI detailsCERSAI REPORT.pdf · uploaded 21 Dec 2021Source
  • 2 OtherCONSENT FORMAT C.pdf · uploaded 21 Dec 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2021 MARCH.pdf · uploaded 12 Jan 2022Source
  • 2 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 31 03 2022.pdf · uploaded 5 Apr 2022Source
  • 3 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 31 12 2021.pdf · uploaded 5 Apr 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2022 07 07 ENGINEER'S CERTIFICATE.pdf · uploaded 20 Jul 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2022 07 07 CA CERTIFICATE.pdf · uploaded 20 Jul 2022Source
  • 4 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 30 06 2022.pdf · uploaded 14 Nov 2022Source
  • 5 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 30 09 2022.pdf · uploaded 14 Nov 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2022 12.pdf · uploaded 27 Jan 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 31 12 2022.pdf · uploaded 27 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE.pdf · uploaded 27 Jan 2023Source
  • 6 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 31 12 2022.pdf · uploaded 27 Jan 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA 2022 12.pdf · uploaded 27 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2022 MARCH.pdf · uploaded 24 Mar 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2023 03.pdf · uploaded 3 May 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2023 03.pdf · uploaded 3 May 2023Source
  • 7 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2023-03-31.pdf · uploaded 3 May 2023Source
  • 8 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2023 06 30.pdf · uploaded 3 Aug 2023Source
  • 3 Copy of the legal title reportTITLE CERTIFICATE 2 2023 11.pdf · uploaded 3 Nov 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC 2 2023 10 27.pdf · uploaded 3 Nov 2023Source
  • 1 Proforma of Agreement for saleAFS 2 2023 11 03.pdf · uploaded 3 Nov 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2023 06.pdf · uploaded 2 Jan 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2022 07.PDF · uploaded 2 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2023 06.pdf · uploaded 2 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 03.pdf · uploaded 2 Jan 2024Source
  • 9 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2023-09-30.pdf · uploaded 2 Jan 2024Source
  • 10 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2023-12-31.pdf · uploaded 2 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2023-03-31_compressed.pdf · uploaded 2 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2023-06-30_compressed.pdf · uploaded 2 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 2023 MARCH.pdf · uploaded 2 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2023 09.pdf · uploaded 9 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2023 12.pdf · uploaded 9 Jan 2024Source
  • 2 Proforma of Agreement for saleAFS 3 2024 01.pdf · uploaded 9 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2023-12-31.pdf · uploaded 23 Mar 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2024 04.pdf · uploaded 8 May 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 04.pdf · uploaded 8 May 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2024 04 25.pdf · uploaded 8 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2023 04.pdf · uploaded 8 May 2024Source
  • 11 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2024 03 31.pdf · uploaded 8 May 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2024-03-31.pdf · uploaded 31 Jul 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (Mahaavir Buildcon LLp).pdf · uploaded 31 Jul 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (B L Chhajer).pdf · uploaded 31 Jul 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (Vijay kumar ranka).pdf · uploaded 31 Jul 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A (Sanjay B Dhariwal).pdf · uploaded 31 Jul 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2024 06.pdf · uploaded 22 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2024 09.pdf · uploaded 22 Oct 2024Source
  • 2 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2024 06 30.pdf · uploaded 22 Oct 2024Source
  • 3 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2024 09 30.pdf · uploaded 22 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured unsecured Finance.pdf · uploaded 22 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 2024 MARCH_1.pdf · uploaded 14 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2024 07.pdf · uploaded 5 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2024 10.pdf · uploaded 5 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2024-06-30_compressed.pdf · uploaded 5 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2024-09-30_compressed.pdf · uploaded 5 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE 2024-12-31.pdf · uploaded 17 Feb 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2024 12 31.pdf · uploaded 17 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured unsecured Finance 2025-04-22.pdf · uploaded 22 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2024 12.pdf · uploaded 24 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT 2025 04.pdf · uploaded 24 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2025 01.pdf · uploaded 24 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE 2025 04.pdf · uploaded 24 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A ENGINEER CERTIFICATE QUALITY ASSURANCE 2024 05.pdf · uploaded 24 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD INVENTORY UPTO 2025 03 31.pdf · uploaded 1 May 2025Source
  • 1 Proforma of Agreement for saleAFS 2025 04.pdf · uploaded 17 May 2025Source
  • Form 1Form 1 - Mahaavir Pride as on June 2025.pdf · uploaded 6 Sep 2025Source
  • Form 2Form 2 - Mahaavir Pride as on June 2025 (SIGNED).pdf · uploaded 6 Sep 2025Source
  • Form 3Form 3 - Mahaavir Pride as on June 2025 (SIGNED).pdf · uploaded 6 Sep 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Mahaavir Pride as on June 2025 (SIGNED).pdf · uploaded 6 Sep 2025Source
  • Form 5 (FY 2024-2025)MahaavirPride_Form 5_FY2425.pdf · uploaded 30 Sep 2025Source
  • Withdrawal Update Form 1Form 1 - Mahaavir Pride as on Sep 2025.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - Mahaavir Pride as on Sept 2025.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - Mahaavir Pride as on Sept 2025.pdf · uploaded 29 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - Mahaavir Pride as on Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 2Form 2 - Mahaavir Pride as on Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 3Form 3 - Mahaavir Pride as on Dec 2025.pdf · uploaded 28 Feb 2026Source
  • Withdrawal Update Form 1Form 1 of Mahaavir Pride as on 31-03-2026.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 2Form 2 of Mahaavir Pride as on 31-03-2026.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 3Form 3 of Mahaavir Pride as on 31-03-2026.pdf · uploaded 18 May 2026Source
  • Withdrawal Update Form 1Form 1 - Mahaavir Pride as on June 2026.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Mahaavir Pride as on June 2026.pdf · uploaded 16 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Mahaavir Pride as on June 2026.pdf · uploaded 16 Jul 2026Source
  • Form 2A (FY 2020-2021)Form 2A 2020-21.pdf · uploaded 1 Aug 2026Source
  • Form 2A (FY 2021-2022)Form 2A 2021-22.pdf · uploaded 1 Aug 2026Source
  • Form 2A (FY 2022-2023)Form 2A 2022-23.pdf · uploaded 1 Aug 2026Source
  • Form 2A (FY 2023-2024)Form 2A 2023-24.pdf · uploaded 1 Aug 2026Source
  • Form 2A (FY 2024-2025)Form 2A 2024-25.pdf · uploaded 1 Aug 2026Source
  • Form 2A (FY 2025-2026)Form 2A 2024-25.pdf · uploaded 1 Aug 2026Source

Technical

  • Document2020 11 09 CC PLAN SHEET 1.pdf · uploaded 21 Nov 2020Source
  • DocumentCC PLAN SHEET 2.pdf · uploaded 21 Nov 2020Source
  • DocumentCC PLAN SHEET 4.pdf · uploaded 21 Nov 2020Source
  • DocumentAMENDED CC APPROVED LAYOUT PLAN S-1.pdf · uploaded 3 Aug 2021Source
  • DocumentAMENDED CC APPROVED LAYOUT PLAN S-1.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-2.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-3.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-4.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-5.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-6.pdf · uploaded 4 Aug 2021Source
  • DocumentAMENDED CC APPROVED PLAN S-7.pdf · uploaded 4 Aug 2021Source
  • DocumentPlan 1_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 2_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 3_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 4_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 5_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 6_compressed.pdf · uploaded 30 Sep 2025Source
  • DocumentPlan 7_compressed.pdf · uploaded 30 Sep 2025Source

Technical (Architect)

  • DocumentFORM 1 ARCHITECT 2024 07.pdf · uploaded 5 Dec 2024Source
  • DocumentFORM 1 ARCHITECT 2024 10.pdf · uploaded 5 Dec 2024Source
  • DocumentFORM 1 ARCHITECT 2024 12.pdf · uploaded 24 Apr 2025Source
  • DocumentFORM 1 ARCHITECT 2025 04.pdf · uploaded 24 Apr 2025Source
  • DocumentForm 1 - Mahaavir Pride as on June 2026.pdf · uploaded 16 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 ENGINEER CERTIFICATE 2024 06.pdf · uploaded 22 Oct 2024Source
  • DocumentFORM 2 ENGINEER CERTIFICATE 2024 09.pdf · uploaded 22 Oct 2024Source
  • DocumentFORM 2 ENGINEER CERTIFICATE 2025 01.pdf · uploaded 24 Apr 2025Source
  • DocumentFORM 2 ENGINEER CERTIFICATE 2025 04.pdf · uploaded 24 Apr 2025Source
  • DocumentForm 2 - Mahaavir Pride as on June 2026.pdf · uploaded 16 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 237/5, 259/4

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK, Office space, Shop, 1BHK496 units in all
Address
S/H. No. 42/2, 237/5, 259/4, Manpada Road, Dombivali EastPIN 421204
Village
Bhopar, Kalyan taluka
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

237/5259/4S/H. NO. 42/2

Boundaries

North
30 Mtr Road
South
Horizon Banquet
East
18 Mtr Road
West
Dhanlaxmi Fabrics

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking496 units

196 of 496 units booked (40%), as the promoter reported to MahaRERA

2BHK · 234 units3BHK · 52 unitsOffice space · 39 unitsShop · 41 units1BHK · 130 units
BuildingTypeCarpet areaUnitsBooked
Mahaavir Pride, Wing - A2BHK63.82 sq m · 687 sq ft5213
Mahaavir Pride, Wing - A2BHK64.01 sq m · 689 sq ft2614
Mahaavir Pride, Wing - A2BHK64.47 sq m · 694 sq ft5216
Mahaavir Pride, Wing - A3BHK83.98 sq m · 904 sq ft2610
Mahaavir Pride, Wing - A3BHK85.19 sq m · 917 sq ft266
Mahaavir Pride, Wing - AOffice space35.67 sq m · 384 sq ft20
Mahaavir Pride, Wing - AOffice space35.77 sq m · 385 sq ft10
Mahaavir Pride, Wing - AOffice space37.07 sq m · 399 sq ft20
Show all 71 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Mahaavir Pride, Wing - AOffice space37.16 sq m · 400 sq ft20
Mahaavir Pride, Wing - AOffice space38.09 sq m · 410 sq ft10
Mahaavir Pride, Wing - AOffice space38.93 sq m · 419 sq ft10
Mahaavir Pride, Wing - AOffice space39.02 sq m · 420 sq ft10
Mahaavir Pride, Wing - AOffice space39.95 sq m · 430 sq ft10
Mahaavir Pride, Wing - AOffice space40.04 sq m · 431 sq ft10
Mahaavir Pride, Wing - AOffice space40.32 sq m · 434 sq ft10
Mahaavir Pride, Wing - AOffice space41.34 sq m · 445 sq ft10
Mahaavir Pride, Wing - AOffice space41.81 sq m · 450 sq ft20
Mahaavir Pride, Wing - AOffice space42.74 sq m · 460 sq ft10
Mahaavir Pride, Wing - AOffice space44.22 sq m · 476 sq ft10
Mahaavir Pride, Wing - AOffice space50.35 sq m · 542 sq ft30
Mahaavir Pride, Wing - AOffice space52.12 sq m · 561 sq ft10
Mahaavir Pride, Wing - AOffice space136.38 sq m · 1,468 sq ft11
Mahaavir Pride, Wing - AShop37.07 sq m · 399 sq ft11
Mahaavir Pride, Wing - AShop38.93 sq m · 419 sq ft11
Mahaavir Pride, Wing - AShop39.76 sq m · 428 sq ft20
Mahaavir Pride, Wing - AShop39.86 sq m · 429 sq ft11
Mahaavir Pride, Wing - AShop41.25 sq m · 444 sq ft11
Mahaavir Pride, Wing - AShop41.34 sq m · 445 sq ft21
Mahaavir Pride, Wing - AShop41.43 sq m · 446 sq ft11
Mahaavir Pride, Wing - AShop42.08 sq m · 453 sq ft21
Mahaavir Pride, Wing - AShop42.64 sq m · 459 sq ft11
Mahaavir Pride, Wing - AShop43.39 sq m · 467 sq ft10
Mahaavir Pride, Wing - AShop43.48 sq m · 468 sq ft10
Mahaavir Pride, Wing - AShop43.76 sq m · 471 sq ft11
Mahaavir Pride, Wing - AShop44.5 sq m · 479 sq ft10
Mahaavir Pride, Wing - AShop44.59 sq m · 480 sq ft10
Mahaavir Pride, Wing - AShop44.96 sq m · 484 sq ft10
Mahaavir Pride, Wing - AShop49.33 sq m · 531 sq ft10
Mahaavir Pride, Wing - AShop50.63 sq m · 545 sq ft31
Mahaavir Pride, Wing - AShop52.4 sq m · 564 sq ft11
Mahaavir Pride, Wing - AShop108.23 sq m · 1,165 sq ft11
Mahaavir Pride, Wing - B1BHK40.23 sq m · 433 sq ft13071
Mahaavir Pride, Wing - B2BHK53.51 sq m · 576 sq ft10445
Mahaavir Pride, Wing - BOffice space35.12 sq m · 378 sq ft10
Mahaavir Pride, Wing - BOffice space35.58 sq m · 383 sq ft10
Mahaavir Pride, Wing - BOffice space35.67 sq m · 384 sq ft30
Mahaavir Pride, Wing - BOffice space35.77 sq m · 385 sq ft10
Mahaavir Pride, Wing - BOffice space35.86 sq m · 386 sq ft10
Mahaavir Pride, Wing - BOffice space37.25 sq m · 401 sq ft10
Mahaavir Pride, Wing - BOffice space38.93 sq m · 419 sq ft10
Mahaavir Pride, Wing - BOffice space39.02 sq m · 420 sq ft10
Mahaavir Pride, Wing - BOffice space40.97 sq m · 441 sq ft10
Mahaavir Pride, Wing - BOffice space42.74 sq m · 460 sq ft10
Mahaavir Pride, Wing - BOffice space45.15 sq m · 486 sq ft10
Mahaavir Pride, Wing - BOffice space50.54 sq m · 544 sq ft10
Mahaavir Pride, Wing - BOffice space51.19 sq m · 551 sq ft10
Mahaavir Pride, Wing - BOffice space108.88 sq m · 1,172 sq ft10
Mahaavir Pride, Wing - BShop32.79 sq m · 353 sq ft10
Mahaavir Pride, Wing - BShop38.37 sq m · 413 sq ft11
Mahaavir Pride, Wing - BShop39.2 sq m · 422 sq ft10
Mahaavir Pride, Wing - BShop39.67 sq m · 427 sq ft10
Mahaavir Pride, Wing - BShop39.76 sq m · 428 sq ft33
Mahaavir Pride, Wing - BShop39.86 sq m · 429 sq ft10
Mahaavir Pride, Wing - BShop39.95 sq m · 430 sq ft11
Mahaavir Pride, Wing - BShop43.29 sq m · 466 sq ft11
Mahaavir Pride, Wing - BShop43.48 sq m · 468 sq ft10
Mahaavir Pride, Wing - BShop45.71 sq m · 492 sq ft11
Mahaavir Pride, Wing - BShop47.66 sq m · 513 sq ft20
Mahaavir Pride, Wing - BShop50.72 sq m · 546 sq ft10
Mahaavir Pride, Wing - BShop56.02 sq m · 603 sq ft11
Mahaavir Pride, Wing - BShop56.86 sq m · 612 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals38

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDesigno Plus—
ArchitectSthapatya Nirmaan—
Chartered accountantKailash Chand Jain & Co—
Chartered accountantManish Kumar Gupta & Co—
EngineerNamdev Rangnath Sutar—
OtherConspel Construction Pvt Ltd—
OtherSunil Bhagane—
Registered real estate agentAbhijeet Anant Mhaskar—
Show all 38 professionalsShow fewer professionals
RoleNameRegistration no.
Registered real estate agentAmol Shantaram Shimpi—
Registered real estate agentAshish Mishrilal Gupta—
Registered real estate agentAtul Balkrishna Kuvalekar—
Registered real estate agentDilip Joshi—
Registered real estate agentHarshad Prabhakar kapse—
Registered real estate agentHome Street Realtors—
Registered real estate agentJayshree Rajesh Baravkar—
Registered real estate agentKiran Bibhishan Borade—
Registered real estate agentKiran Pandharinath Patil—
Registered real estate agentManish Jayprakash Dubey—
Registered real estate agentMohit Vasant Sanghvi—
Registered real estate agentNathuram Bheraji Bhatia—
Registered real estate agentNilesh Narendra Mehta—
Registered real estate agentNobroker Technologies Solutions Private Limited—
Registered real estate agentPriti Lalit Nemade—
Registered real estate agentPropertypistol Realty Private Limited—
Registered real estate agentRajdeo Ramroop Singh—
Registered real estate agentRanjiv Ashok Singh—
Registered real estate agentRavina Indraprakash Upadhyay—
Registered real estate agentSachin Arvind Thakkar—
Registered real estate agentSandip Dattaram Mohandas—
Registered real estate agentSeed Realty Private Limited—
Registered real estate agentSharad Shamrao Gavali—
Registered real estate agentShrikant Narayan Pakhle—
Registered real estate agentShubham Harikesh Varma—
Registered real estate agentSudhir Dharmaji Thorat—
Registered real estate agentSwapna Vinay Machha—
Registered real estate agentTushar Suresh Shingote—
Registered real estate agentVivek Rajendra Chavan—
Registered real estate agentVmansions India Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology