Khushi Axis World
Deedo IDDP-THN-9TGXCompletion was pushed back 2 years, to Dec 2026; no MahaRERA orders on record; 70% of its units are booked.
Bhiwandi, Maharashtra 421302 · Promoter: Khushi Axis Infratech LLP
Completion was pushed back 2 years, to Dec 2026
- This projectRegistered 15 Oct 2021, completion promised 31 Dec 2024, revised to 31 Dec 2026.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700031265
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700031265 | 15 Oct 2021 | 31 Dec 2024 | 31 Dec 2026 | Khushi Axis Infratech LLP | Project page |
Documents80
2 documents held by Deedo, 78 filings listed on MahaRERA's project page
Finance
- PAN CardKHUSHI AXIS INFRATECH PAN CARD 001.pdf · uploaded 12 Sep 2021Source
Legal
Show all 80 documentsShow fewer documents
Migrated
- 1 Declaration in FORM B8_FORM_B.pdf · uploaded 7 Sep 2021Source
- 1 PAN CardKHUSHI AXIS INFRATECH PAN CARD 001.pdf · uploaded 12 Sep 2021Source
- 1 Copy of the legal title reportTITLE.pdf · uploaded 12 Sep 2021Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT-1.pdf · uploaded 12 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentLAYOUT-2.pdf · uploaded 12 Sep 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentLAYOUT-3.pdf · uploaded 12 Sep 2021Source
- 3 Building Plan Approval / NA Order for plotted developmentLAYOUT-4.pdf · uploaded 12 Sep 2021Source
- 1 Details of encumbrancesENCRUBANCES.pdf · uploaded 17 Sep 2021Source
- 1 Declaration about Commencement CertificateCOMMENCEMENT.pdf · uploaded 17 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 17 Sep 2021Source
- 2 Copy of the legal title reportTITLE DECL.pdf · uploaded 5 Oct 2021Source
- 3 Copy of the legal title reportTITLE DELEC.pdf · uploaded 5 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentKHUSHI CC.pdf · uploaded 5 Oct 2021Source
- 1 Proforma of Allotment letterRERA-FLAT- RESIDENTIAL - DRAFT.pdf · uploaded 5 Oct 2021Source
- 2 Proforma of Allotment letterRERA-FLAT- COMMERCIAL - DRAFT.pdf · uploaded 5 Oct 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)KHUSHI_ARCHITECT_CERTIFICATE.pdf · uploaded 5 Apr 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)KHUSHI_Engineer_Certificate.pdf · uploaded 5 Apr 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)KHUSHI_RERA_FORM_3_311222.pdf · uploaded 5 Apr 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Upto Mar 23_compressed.pdf · uploaded 15 Sep 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Upto Jun 23_compressed.pdf · uploaded 15 Sep 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture certificate .pdf · uploaded 18 Sep 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's certificate .pdf · uploaded 18 Sep 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineer certificate_FORM 2A.pdf · uploaded 21 Dec 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 27 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate .pdf · uploaded 27 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Scan 31-12-2023_compressed.pdf · uploaded 7 May 2024Source
- 1 Proforma of Agreement for saledraft sale agreement.pdf · uploaded 14 May 2024Source
- 3 Proforma of Allotment letterallotment letter.pdf · uploaded 14 May 2024Source
- 2 Details of encumbrancesEncumbrance Certificate and Index II.pdf · uploaded 22 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 31-03-2023.pdf · uploaded 17 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 31-03-2022.pdf · uploaded 17 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineer certificate 31-03-2024.pdf · uploaded 20 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 21 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 17 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 17 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 sep 24.pdf · uploaded 25 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 dec 24.pdf · uploaded 25 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDiscolsure inventory.pdf · uploaded 25 Jan 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)format A bank letter.pdf · uploaded 25 Jan 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A DOI.pdf · uploaded 25 Jan 2025Source
- 1 Declaration in FORM Bform B.pdf · uploaded 30 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)2A form 2021-2022 (1).pdf · uploaded 30 Jan 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2A form 2023-2024 (1).pdf · uploaded 30 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Annexue A.pdf · uploaded 26 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2 Annexure B.pdf · uploaded 26 Apr 2025Source
- Form 2A (FY 2024-2025)Khushi Axis World New 2A 31-03-2025.pdf · uploaded 25 Sep 2025Source
- Withdrawal Update Form 1Form 1 june 25.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 2Form 2 june 25.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 3form 3 june 25.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1KHUSHI ARCH 01-10-25.pdf · uploaded 11 Nov 2025Source
- Withdrawal Update Form 2KHUSHI ENG 01-10-25.pdf · uploaded 11 Nov 2025Source
- Withdrawal Update Form 3form 3 june 25.pdf · uploaded 11 Nov 2025Source
- Withdrawal Update Form 1Architecht Certificate.pdf · uploaded 18 Feb 2026Source
- Withdrawal Update Form 2Engineer certificate.pdf · uploaded 18 Feb 2026Source
- Withdrawal Update Form 3For 3 CA.pdf · uploaded 18 Feb 2026Source
- Withdrawal Update Form 1form 1.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 3form 3 (29).pdf · uploaded 11 Jun 2026Source
- Withdrawal Update Form 1ARCHITECT FORM.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 3form 3.pdf · uploaded 15 Jul 2026Source
- Form 2A (FY 2025-2026)form 2A.pdf · uploaded 5 Oct 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals21/1/D MANKOLI NAKA, 211D MANKOLI NAKA
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —332 units in all
- Address
- Survey No.21/1/C, 21/1/E, 21/1/D Mankoli Naka, Bhiwandi, 421302, Mankoli Naka, BhiwandiPIN 421302
- Village
- Amane, Bhiwandi taluka
- Location
- 19.24082, 73.04593
- Designated bank account
- 109
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- 15 Mts Wide Dp Road
- South
- 45 Mts Wide Dp Road
- East
- Sn21 House No 2-3 And Sno 25
- West
- Sn 21
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking332 units
332 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Khushi Axis World | — | — | 269 |
| Khushi Axis World A Wing | — | — | 63 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals10
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Kk And Associates | — |
| Chartered accountant | Kumar Shah | — |
| Chartered accountant | Nehali Dhaval Doshi | — |
| Engineer | Kk And Associates | — |
| Other | Kk And Associates | — |
| Other | Rafiullah Abdulhusain Khan | — |
| Other | Saleem Ahmad | — |
| Other | Shaikh Shahadat Abdul Kadar | — |
| Other | Shoebansari | — |
| Other | Vishweswar Dyal Bhadva | — |
Source: MahaRERA project page. Contact details are not shown.