Skip to content
Others · 1 building · 47 unitsRERA P51700046876

Salasar Crystal

Deedo IDDP-THN-04N2

Its promised completion date, Jun 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 53% of its units are booked.

Bhayandar, Thane 401101 · by Salasar Samrudhi Realty Private Limited

Delivery5 mo past duePromised Jun 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales53% booked25 of 47 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Jun 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 16 Sep 2022, completion promised 30 Jun 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700046876
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170004687616 Sep 202230 Jun 202630 Jun 2026Salasar Samrudhi Realty Private LimitedProject page
Documents114

1 document held by Deedo, 113 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 1 Sep 2022Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 1 Sep 2022Source
  • Declaration Form BAffidavit Cum Declaration.pdf · uploaded 1 Sep 2022Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 1 Sep 2022Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 1 Sep 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 1 Sep 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommCert.pdf · uploaded 1 Sep 2022Source
Show all 114 documentsShow fewer documents

Migrated

  • 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE.pdf · uploaded 1 Sep 2022Source
  • 1 Declaration in FORM BAffidavit Cum Declaration.pdf · uploaded 1 Sep 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Cert.pdf · uploaded 1 Sep 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 ENGINEER CERTIFTCATE.pdf · uploaded 1 Sep 2022Source
  • 1 CERSAI detailsCERSAI Asset Based.pdf · uploaded 1 Sep 2022Source
  • 2 CERSAI detailsCersai Declaration.pdf · uploaded 1 Sep 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 1 Sep 2022Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 1 Sep 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank.pdf · uploaded 1 Sep 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrances Concerned to Finance.pdf · uploaded 3 Sep 2022Source
  • 1 b Details of encumbrances concerned to LegalEncumbrances Concerned to Legal.pdf · uploaded 3 Sep 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report Allotment Letter.pdf · uploaded 3 Sep 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report Agreement for Sale.pdf · uploaded 3 Sep 2022Source
  • 1 Other – TechnicalCertificate of Incorporation after change of name.PDF · uploaded 3 Sep 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout Plan 1.pdf · uploaded 9 Sep 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentLayout Plan 2.pdf · uploaded 9 Sep 2022Source
  • 2 Deviation Report with respect to model copy of AgreementSALE AGREEMENT.pdf · uploaded 9 Sep 2022Source
  • 2 Other – TechnicalSALE AGREEMENT.pdf · uploaded 9 Sep 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jan 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 20 Jan 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory.pdf · uploaded 20 Jan 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Kunal.pdf · uploaded 20 Jan 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Niranjan.pdf · uploaded 20 Jan 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Narayan.pdf · uploaded 20 Jan 2023Source
  • 1 Proforma of Agreement for saleSALE AGREEMENT.pdf · uploaded 20 Jan 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect.pdf · uploaded 19 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer.pdf · uploaded 19 Apr 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A.pdf · uploaded 19 Apr 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Details.pdf · uploaded 19 Apr 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 19 Apr 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Aug 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 2 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 2 Aug 2023Source
  • 3 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold.pdf · uploaded 2 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 Aug 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 25 Oct 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 25 Oct 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 25 Oct 2023Source
  • 4 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 25 Oct 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (2).pdf · uploaded 25 Oct 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 25 Jan 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 25 Jan 2024Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 25 Jan 2024Source
  • 5 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 25 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate.pdf · uploaded 29 Jan 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 2022-23.pdf · uploaded 7 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 27 Apr 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 27 Apr 2024Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 27 Apr 2024Source
  • 6 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 27 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 29 Apr 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 3 Aug 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FROM 2.pdf · uploaded 3 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FROM 2A.pdf · uploaded 3 Aug 2024Source
  • 7 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 3 Aug 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA cert.pdf · uploaded 3 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Cert.pdf · uploaded 8 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Cert.pdf · uploaded 8 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Eng Cert.pdf · uploaded 8 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD SIGNED.pdf · uploaded 8 Nov 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Site Sup.pdf · uploaded 8 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Arch Cert.pdf · uploaded 28 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Cert.pdf · uploaded 28 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng Cert.pdf · uploaded 28 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 28 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Site Super.pdf · uploaded 28 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 22 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 22 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 22 Apr 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 3Form 3 30 Jun 2025.pdf · uploaded 17 Dec 2025Source
  • Form 2A (FY 2024-2025)Form 2A FY 2024-25.pdf · uploaded 6 Mar 2026Source
  • Form 5 (FY 2024-2025)RERA FORM 5 FY 2024-25.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 1Form 1 31032026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 2Form 2 31032026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 3Form 3 31032026.pdf · uploaded 9 Jul 2026Source
  • Withdrawal Update Form 1Form 1 June 2026.pdf · uploaded 22 Aug 2026Source
  • Withdrawal Update Form 2Form 2 June 2026.pdf · uploaded 22 Aug 2026Source
  • Withdrawal Update Form 3Form 3 June 2026.pdf · uploaded 22 Aug 2026Source
  • Form 2A (FY 2025-2026)FORM 2A FY 2025-26.pdf · uploaded 27 Aug 2026Source
  • Form 5 (FY 2025-2026)FORM 5 FY 2025-26.pdf · uploaded 27 Aug 2026Source

Technical

  • DocumentLayout Plan.pdf · uploaded 1 Sep 2022Source
  • Other – TechnicalCertificate of Incorporation after change of name.PDF · uploaded 3 Sep 2022Source
  • DocumentLayout Plan 1.pdf · uploaded 9 Sep 2022Source
  • DocumentLayout Plan 2.pdf · uploaded 9 Sep 2022Source
  • Other – TechnicalSALE AGREEMENT.pdf · uploaded 9 Sep 2022Source

Technical (Architect)

  • DocumentForm 1 Arch Cert.pdf · uploaded 8 Nov 2024Source
  • DocumentForm 1 Arch Cert.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 1 June 2026.pdf · uploaded 20 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2 Eng Cert.pdf · uploaded 8 Nov 2024Source
  • DocumentForm 2 Eng Cert.pdf · uploaded 28 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 22 Apr 2025Source
  • DocumentForm 2 June 2026.pdf · uploaded 20 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel NEW SURVEY NO. 219/9, OLD SURVEY NO. 566/9

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, Office space, Shop47 units in all
Address
Old Survey No. 566/9, New Survey No. 219/9, Maheshwari Bhavan Marg, S V Road, Near Planetaria ComplexPIN 401101
Village
Bhayandar, Thane taluka
Land area for this project
591 sq m (6,360 sq ft)
Permissible built-up area
3,293 sq m (35,447 sq ft)
Sanctioned built-up area
3,293 sq m (35,447 sq ft)
Recreational open space
451 sq m (4,851 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

NEW SURVEY NO. 219/9OLD SURVEY NO. 566/9

Land as published on MahaRERA's project page

OLD SURVEY NO. 566/9, NEW SURVEY NO. 219/9

Boundaries

North
18 OMt DP ROAD
South
Survey No 205
East
Survey No 566 Hissa No 6
West
Survey No 566 Hissa No 8

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking47 units

25 of 47 units booked (53%), as the promoter reported to MahaRERA

1BHK · 21 units1RK · 2 units2BHK · 18 unitsOffice space · 2 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1BHK43.43 sq m · 467 sq ft2114
1RK43.38 sq m · 467 sq ft20
2BHK59.29 sq m · 638 sq ft189
Office space28.58 sq m · 308 sq ft10
Office space59.29 sq m · 638 sq ft10
Shop9.97 sq m · 107 sq ft10
Shop10.27 sq m · 111 sq ft11
Shop12.72 sq m · 137 sq ft10
Shop13.71 sq m · 148 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectTej's' Consultants—
Chartered accountantKarta And Company—
Chartered accountantRavi Bhagwatiprasad Gupta—
EngineerAkhilesh Shukla—
EngineerRajesh B Dubey—
OtherKalyani Rajeev Tiwari—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology