Antaraa
Deedo IDDP-THN-RHGVMahaRERA shows it completed; no MahaRERA orders on record; 24% of its units are booked.
Belapur, Thane 400614 · by Sai Infrastrcuture
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed
- This projectRegistered 17 Jan 2023, completion promised 31 Dec 2024.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP51700048795
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700048795 | 17 Jan 2023 | 31 Dec 2024 | 31 Dec 2024 | Sai Infrastrcuture | Project page |
Documents70
2 documents held by Deedo, 68 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardPan Card_SAI Infrastructure.pdf · uploaded 10 Dec 2022Source
Legal
Show all 70 documentsShow fewer documents
Migrated
- 1 b Details of encumbrances concerned to LegalLegal.pdf · uploaded 10 Dec 2022Source
- 1 Copy of Layout Approval (in case of layout)Approved Layout .pdf · uploaded 10 Dec 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentApproved Layout .pdf · uploaded 10 Dec 2022Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 10 Dec 2022Source
- 1 Declaration in FORM BForm B.pdf · uploaded 10 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_ARCHITECTS CERTIFICATE.pdf · uploaded 10 Dec 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Engg Certificate.pdf · uploaded 10 Dec 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_CA .pdf · uploaded 10 Dec 2022Source
- 1 Proforma of Allotment letterANNEXURE A (Allotment letter).pdf · uploaded 10 Dec 2022Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Sheet for Agreemet for Sale (under 1MB) 1-8 pages.pdf · uploaded 10 Dec 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation sheet of Allotment letter.pdf · uploaded 12 Dec 2022Source
- 1 Proforma of Agreement for saleAgreement for Sale.pdf · uploaded 20 Dec 2022Source
- 2 Deviation Report with respect to model copy of AgreementDeviation Sheet for Agreement For Sale (under 1 MB) 9-16 Pages.pdf · uploaded 20 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceFinancial Encumbrance.pdf · uploaded 3 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalFinancial Encumbrance.pdf · uploaded 3 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 3 Jan 2023Source
- 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 3 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account.pdf · uploaded 6 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosures of AS.pdf · uploaded 10 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosures of MBS.pdf · uploaded 10 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Antaraa.pdf · uploaded 6 Jul 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 ENGINEER CERTIFICATE (1).pdf · uploaded 6 Jul 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)quality_assurance-.pdf · uploaded 6 Jul 2023Source
- 1 Disclosure of sold/ booked inventorySold and Unsold March.pdf · uploaded 6 Jul 2023Source
- 2 Disclosure of sold/ booked inventorySold and Unsold June.pdf · uploaded 6 Jul 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -3 CA CERTIFICATE March 23.pdf · uploaded 12 Jul 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Antaraa June.pdf · uploaded 18 Jul 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June.pdf · uploaded 2 Aug 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June (2).pdf · uploaded 2 Aug 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A June.pdf · uploaded 2 Aug 2023Source
- 3 Disclosure of sold/ booked inventorySoldUnsold June.pdf · uploaded 2 Aug 2023Source
- 4 Disclosure of sold/ booked inventorySoldunsold June (2).pdf · uploaded 2 Aug 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June.pdf · uploaded 2 Aug 2023Source
- 2 Copy of Layout Approval (in case of layout)2 Project Information.pdf · uploaded 13 Sep 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentANTARAA_Revised CC.pdf · uploaded 13 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Antaraa.pdf · uploaded 30 Sep 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 September.pdf · uploaded 12 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Antaraa_Form 3.pdf · uploaded 20 Oct 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (1).pdf · uploaded 25 Oct 2023Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)QUALITY ASSURANCE FORM 2A.pdf · uploaded 25 Oct 2023Source
- 5 Disclosure of sold/ booked inventoryAntara Sold Unsold.pdf · uploaded 27 Oct 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 December 2023 Antaraa.pdf · uploaded 9 Jan 2024Source
- 6 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY-31-12-2023.pdf · uploaded 12 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Antaraa December 2023.pdf · uploaded 20 Jan 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Antaraa December 2023.pdf · uploaded 20 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 Antaraa December 2023.pdf · uploaded 23 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Antaraa Form 1 March.pdf · uploaded 1 Apr 2024Source
- 7 Disclosure of sold/ booked inventorySOL UNSOLD-March 2024.pdf · uploaded 1 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Antaraa March 2024.pdf · uploaded 22 Apr 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Antaraa Rera Certificate 3rd july 2024.pdf · uploaded 3 Jul 2024Source
- 8 Disclosure of sold/ booked inventoryINVENTORY.pdf · uploaded 3 Jul 2024View
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_Sai Infra_Antara_Q1_FY 24-25 (2) (1)_compressed.pdf · uploaded 19 Jul 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Antaraa Form 2 June 2024.pdf · uploaded 20 Jul 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAntaraa OC.pdf · uploaded 7 Oct 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4 Antaraa (1).pdf · uploaded 5 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 antara.pdf · uploaded 5 Nov 2024Source
Technical
Technical (Architect)
- DocumentAntaraa Rera Certificate 3rd july 2024.pdf · uploaded 3 Jul 2024Source
Technical (Engineer)
- DocumentAntaraa Form 2 June 2024.pdf · uploaded 20 Jul 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 286/12
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK21 units in all
- Address
- 286/12, Shahbaz, BelapurPIN 400614
- Village
- Navi Mumbai (M Corp.), Thane taluka
- Land area for this project
- 760 sq m (8,181 sq ft)
- Permissible built-up area
- 2,278 sq m (24,520 sq ft)
- Sanctioned built-up area
- 2,162 sq m (23,272 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
286/12
Boundaries
- North
- Survey No 286 Hissa no 7
- South
- 15 Meter Road
- East
- Survey No 287
- West
- Survey no 286 Hissa no 11
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking21 units
5 of 21 units booked (24%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 3BHK | 76.8 sq m · 827 sq ft | 7 | 1 |
| 3BHK | 92.82 sq m · 999 sq ft | 7 | 1 |
| 3BHK | 98.96 sq m · 1,065 sq ft | 7 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Piyush Tak | — |
| Chartered accountant | S V Shanbag | — |
| Engineer | Latif Ansari | — |
Source: MahaRERA project page. Contact details are not shown.