Skip to content

Krishna Nayan Complex Phase I

Active

Badlapur (M Cl), Thane 421503 |Promoter: Shreeji Builders And Developers

25 May 2024Registered with MahaRERA
31 Dec 2027Promised completion
5Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
5
Land area for this project
3,390 sq m (36,488 sq ft)
Permissible built-up area
9,938 sq m (1,06,967 sq ft)
Sanctioned built-up area
9,938 sq m (1,06,967 sq ft)
Recreational open space
339 sq m (3,649 sq ft)
Planning authority
Kulgaon Badlapur Nagar Parishad
Address
Survey No 37, Hissa No 4A, Survey No 37, Hissa No 5/A/6, Plot No 5, Survey No.37, Hissa No 4A, Survey No.37, Hissa No 5/A/6, Plot No.5, Village - Shirgaon, Taluka Ambernath, BadlapurPIN 421503
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.16452, 73.23275
Krishna Nayan Complex Phase I is at latitude 19.16452, longitude 73.23275.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2027

Registered
25 May 2024
Promised
31 Dec 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170005628825 May 202431 Dec 2027—Shreeji Builders And DevelopersProject page

5 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A8—
Wing B8—
Wing C7—
Wing D8—
Wing E8—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing AClosed/Covered00000
Wing AOpen Space3660042
Wing BClosed/Covered00000
Wing BOpen Space3080038
Wing CClosed/Covered00000
Wing COpen Space45220067
Wing DClosed/Covered00000
Wing DOpen Space36120048
Wing EClosed/Covered00000
Wing EOpen Space3080038

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wing A

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Wing B

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Wing C

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
  • Sanitary Fittings within the flats / premises30%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Show all 6 buildings and common areasShow fewer buildings and common areas

Wing D

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing E

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyMJP WILL PROVIDED WATER CONNECTION AFTER OC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)SEPTIC TANK0%
  • Storm Water DrainsSTORM WATER DRAINS0%
  • Landscaping & Tree PlantingTREE PLANTING0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARVESTING WORK0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsFIRE PROTECTION AND FIRE SAFETY REQUIREMENTS0%
  • Electrical meter room, sub-station, receiving stationMETER ROOM PROVIDED0%
  • Aggregate area of recreational Open SpaceAS PER PLAN0%
  • Open ParkingAS PER PLAN0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

59 documents held by Deedo, 55 filings listed on MahaRERA's project page

Encumbrance details (3)

Commencement certificate (2)

Form 1 (10)

Show all 114 documentsShow fewer documents

Form 1 (10)

Form 2 (10)

Other (22)

Allotment letter (2)

Form B

Title report (2)

Registration certificate

Form 5 (2)

Form 2A

Layout plan

Building plan (2)

Document library

  • a Details of encumbrances concerned to FinanceNo Encumberance.pdf · uploaded 16 Mar 2024View
  • b Details of encumbrances concerned to LegalNo Encumberance.pdf · uploaded 16 Mar 2024View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 16 Mar 2024View
  • Declaration about Commencement CertificateForm D (1).pdf · uploaded 16 Mar 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 16 Mar 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 16 Mar 2024View
  • CERSAI detailsCersai Declaration.pdf · uploaded 16 Mar 2024View
  • Proforma of Agreement for saleAFS_11zon.pdf · uploaded 16 Mar 2024View
  • Deviation Report with respect to Allotment letterNo Deviation Allotment.pdf · uploaded 16 Mar 2024View
  • Deviation Report with respect to model copy of AgreementNo Deviation Agreement.pdf · uploaded 16 Mar 2024View
  • Copy of Layout Approval (in case of layout)scan document 10436 Sheet 1_11zon.pdf · uploaded 18 Mar 2024View
  • Building Plan Approval / NA Order for plotted developmentscan document 10435 Sheet 2_11zon.pdf · uploaded 18 Mar 2024View
  • Building Plan Approval / NA Order for plotted developmentscan document 10434 Sheet 3_11zon.pdf · uploaded 18 Mar 2024View
  • Declaration in FORM BForm B Promoter.pdf · uploaded 18 Mar 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameformat a.pdf · uploaded 20 Mar 2024View
  • CERSAI detailsCERSAI_Search_Report_200301236884_For_Asset_Based_Search_20_03_2024_17_28_47_777.pdf · uploaded 20 Mar 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Kalpesh.pdf · uploaded 20 Mar 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Vipul Shah (1).pdf · uploaded 26 Mar 2024View
  • Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 26 Mar 2024View
  • Other – TechnicalAnnexure A.pdf · uploaded 12 Apr 2024View
  • Copy of the legal title reportLegal Title Clarification.pdf · uploaded 9 May 2024View
  • Copy of the legal title reportLegal Title.pdf · uploaded 14 May 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31032024.pdf · uploaded 25 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 27062024.pdf · uploaded 25 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30092024.pdf · uploaded 25 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30062024_11zon.pdf · uploaded 25 Nov 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30092024_11zon.pdf · uploaded 25 Nov 2024View
  • a Details of encumbrances concerned to FinanceEncumbrance Cert.pdf · uploaded 9 Jan 2025View
  • b Details of encumbrances concerned to LegalEncumbrance Cert.pdf · uploaded 9 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shreeji B and D_11zon.pdf · uploaded 10 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shreeji B and D.pdf · uploaded 10 Jan 2025View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 13 Mar 2025View
  • Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 13 Mar 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Shreeji Builders and Developers Q4.pdf · uploaded 19 Apr 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shreeji Builders and Developers Q4.pdf · uploaded 19 Apr 2025View
  • Withdrawal Update Form 1Form 1 30062025.pdf · uploaded 19 Jul 2025View
  • Withdrawal Update Form 2Form 2 30062025.pdf · uploaded 19 Jul 2025View
  • Form 5 (FY 2024-2025)Form 5 Shreeji Builders & Developers Signed.pdf · uploaded 30 Sep 2025View
  • Withdrawal Update Form 1Form 1 shreeji build And dev Signed.pdf · uploaded 20 Jan 2026View
  • Withdrawal Update Form 2form 2 shreeji builders And dec Signed.pdf · uploaded 20 Jan 2026View
  • Withdrawal Update Form 1Form 1.pdf · uploaded 14 Apr 2026View
  • Withdrawal Update Form 2Form 2.pdf · uploaded 14 Apr 2026View
  • Withdrawal Update Form 1Shreeji Build and Dev Form 1.pdf · uploaded 23 Apr 2026View
  • Withdrawal Update Form 2Shreeji Bldrs And Dev form 2.pdf · uploaded 23 Apr 2026View
  • Withdrawal Update Form 1shreeji Build And dev form 1.pdf · uploaded 21 Jul 2026View
  • Withdrawal Update Form 2Form 2 Shreeji Builders and Developers Q1.pdf · uploaded 21 Jul 2026View
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 20 Aug 2026View
  • Form 5 (FY 2025-2026)Form 5 Signed Shreeji Builder and developers.pdf · uploaded 30 Sep 2026View

Promoter documents

  • Declaration Form BForm B Promoter.pdf · uploaded 18 Mar 2024View
  • Legal Title reportLegal Title Clarification.pdf · uploaded 9 May 2024View
  • Legal Title reportLegal Title.pdf · uploaded 14 May 2024View

Technical documents

  • Layout Approvalscan document 10436 Sheet 1_11zon.pdfView
  • Building Plan Approvalscan document 10435 Sheet 2_11zon.pdfView
  • Building Plan Approvalscan document 10434 Sheet 3_11zon.pdfView

Proforma allotment letter

  • Proforma allotment letterDraft Allotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Badlapur (M Cl), Ambarnath taluka

Survey, CTS, gat or plot numbers

5Hissa No 4AHissa No 5/A/6Plot No 5Survey No 37

As published on MahaRERA's project page

Survey No 37,Hissa No 4A, Survey No 37, Hissa No 5/A/6, Plot No 5

Boundaries

North
Khatri Complex
South
Vaibhav Lakshmi Co Op Housing Soc Ltd 9 Mtr Road
East
Sachin Sameer Co-Op Housing Society Ltd
West
Lakshminarayan Bunglow

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaj Associates—
Chartered accountantMukesh Gurnani—
Chartered accountantVRP & Associates—
EngineerAtul Kudtarkar And Associates Pvt Ltd—
EngineerSharanbasappa Kalshetty—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology