Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 15% of its units are booked.

Ambarnath, Maharashtra 400102 · Promoter: Dipti Home Makers Pvt Ltd

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales15% booked35 of 230 units · as the promoter reported to MahaRERA
Dipti SkyCity project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2027

  • P51700008856Registered 19 Aug 2017, completion promised 31 Jul 2023, and still not shown completed today.
  • P51700048627Registered 10 Jan 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

2 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations2
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000885619 Aug 201731 Jul 202331 Jul 2023Dipti Home Makers Pvt LtdProject page
P5170004862710 Jan 202331 Dec 202630 Apr 2027Dipti Home Makers Pvt LtdProject page
Documents163

2 documents held by Deedo, 161 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP51700008856 · 9 Sep 2021ViewSource
  • Registration certificateP51700048627 · 10 Jan 2023ViewSource

Finance

  • PAN CardP51700048627 · DHMPL PAN CARD.pdf · uploaded 6 Oct 2022Source

Legal

  • Legal Title reportP51700008856 · title.pdf · uploaded 27 Jul 2017Source
  • Declaration Form BP51700008856 · Declaration.pdf · uploaded 27 Jul 2017Source
  • OtherP51700008856 · final OC Himalaya.pdf · uploaded 6 Feb 2018Source
  • OtherP51700008856 · OC Satpura Building 1.pdf · uploaded 26 Mar 2018Source
  • Declaration Form BP51700048627 · Scan-4-5.pdf · uploaded 8 Oct 2022Source
Show all 163 documentsShow fewer documents

Legal

  • Legal Title reportP51700048627 · Title certificate.pdf · uploaded 24 Nov 2022Source
  • Other – LegalP51700048627 · Declaration cum Undertaking 25042025.pdf · uploaded 25 Apr 2025Source
  • Other – LegalP51700048627 · Declaration Rationale account change 24042025.pdf · uploaded 25 Apr 2025Source
  • Other – LegalP51700048627 · Format A 24042025.pdf · uploaded 25 Apr 2025Source
  • Other – LegalP51700048627 · Form 3 Opal Bay Revised 25042025.pdf · uploaded 25 Apr 2025Source
  • Other – LegalP51700048627 · Form 3 Sky City March 2025_compressed.pdf · uploaded 25 Apr 2025Source
  • Other – LegalP51700048627 · Declaration cum undertaking Sky City 24042025.pdf · uploaded 25 Apr 2025Source

Migrated

  • 1 Copy of the legal title reportP51700008856 · title.pdf · uploaded 27 Jul 2017Source
  • 1 Details of encumbrancesP51700008856 · No encumbrances.pdf · uploaded 27 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P51700008856 · 1.pdf · uploaded 27 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)P51700008856 · 2 com.pdf · uploaded 27 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)P51700008856 · 3.pdf · uploaded 27 Jul 2017Source
  • 1 Building Plan Approval (IOD)P51700008856 · 1.pdf · uploaded 27 Jul 2017Source
  • 2 Building Plan Approval (IOD)P51700008856 · 2 com.pdf · uploaded 27 Jul 2017Source
  • 3 Building Plan Approval (IOD)P51700008856 · 3.pdf · uploaded 27 Jul 2017Source
  • 1 Declaration in FORM BP51700008856 · Declaration.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P51700008856 · Arch Certific.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P51700008856 · Eng Certi.pdf · uploaded 27 Jul 2017Source
  • 1 Proforma of Allotment letterP51700008856 · Sample Allotment Letter.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of CA (Form 3)P51700008856 · Form 3 - Ambernath 1 to 3.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterP51700008856 · Draft Agreement.pdf · uploaded 31 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700008856 · final OC Himalaya.pdf · uploaded 6 Feb 2018Source
  • 1 OtherP51700008856 · final OC Himalaya.pdf · uploaded 6 Feb 2018Source
  • 2 OtherP51700008856 · OC Satpura Building 1.pdf · uploaded 26 Mar 2018Source
  • 1 Certificates of Architect (Form 4)P51700008856 · FORM 4.pdf · uploaded 19 Dec 2018Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP51700008856 · OC Satpura Building No 1.pdf · uploaded 26 Oct 2021Source
  • 1 PAN CardP51700048627 · DHMPL PAN CARD.pdf · uploaded 6 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceP51700048627 · Scan-1.pdf · uploaded 8 Oct 2022Source
  • 1 b Details of encumbrances concerned to LegalP51700048627 · Scan-1.pdf · uploaded 8 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)P51700048627 · Approved Plan All Pages.pdf · uploaded 8 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentP51700048627 · Approved Plan All Pages.pdf · uploaded 8 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentP51700048627 · CC.pdf · uploaded 8 Oct 2022Source
  • 1 Declaration about Commencement CertificateP51700048627 · Scan-3.pdf · uploaded 8 Oct 2022Source
  • 1 Declaration in FORM BP51700048627 · Scan-4-5.pdf · uploaded 8 Oct 2022Source
  • 1 Proforma of Allotment letterP51700048627 · Allotment Letter.pdf · uploaded 8 Oct 2022Source
  • 2 a Details of encumbrances concerned to FinanceP51700048627 · Undertaking for CERSAI.pdf · uploaded 23 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalP51700048627 · Undertaking for CERSAI.pdf · uploaded 23 Nov 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700048627 · Format A for unique Bank Account.pdf · uploaded 23 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterP51700048627 · Deviation Report for AL.pdf · uploaded 23 Nov 2022Source
  • 1 Copy of the legal title reportP51700048627 · Title certificate.pdf · uploaded 24 Nov 2022Source
  • 3 a Details of encumbrances concerned to FinanceP51700048627 · No encumbrances.pdf · uploaded 6 Dec 2022Source
  • 3 b Details of encumbrances concerned to LegalP51700048627 · No encumbrances.pdf · uploaded 6 Dec 2022Source
  • 1 CERSAI detailsP51700048627 · Undertaking for CERSAI.pdf · uploaded 6 Dec 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 with UDIN.pdf · uploaded 14 Dec 2022Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameP51700048627 · Format A CKS.pdf · uploaded 14 Dec 2022Source
  • 1 Proforma of Agreement for saleP51700048627 · Agreement for Sale Bldg 7 15th Dec.pdf · uploaded 16 Dec 2022Source
  • 1 Deviation Report with respect to model copy of AgreementP51700048627 · Deviation Report for AFS.pdf · uploaded 16 Dec 2022Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP51700048627 · Disclosure of Directors 2nd Jan 2023_compressed.pdf · uploaded 2 Jan 2023Source
  • 4 a Details of encumbrances concerned to FinanceP51700048627 · RERA Encumbrance certificate 24th Feb 2023.pdf · uploaded 25 Feb 2023Source
  • 4 b Details of encumbrances concerned to LegalP51700048627 · RERA Encumbrance certificate 24th Feb 2023.pdf · uploaded 25 Feb 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 31st Dec 2022.pdf · uploaded 29 May 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 31st March 2023.pdf · uploaded 29 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Annexure A-Form 1 June 2023.pdf · uploaded 5 Sep 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Dipti Skycity Form 2 30th june 2023.pdf · uploaded 5 Sep 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · FORM 1 - ANNEXURE A - 30-09-2023.pdf · uploaded 25 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · FORM 2 - ANNEXURE B - 30-09-2023.pdf · uploaded 25 Oct 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P51700048627 · Form 2A 2022-23.pdf · uploaded 25 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 30-09-2023.pdf · uploaded 25 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 RERA June 2023.pdf · uploaded 11 Nov 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700048627 · FORM 5 ANNUAL AUDIT REPORT OF STATUTORY.pdf · uploaded 22 Nov 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 - Annexure B - 31-03-2023.pdf · uploaded 29 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 March 2023.pdf · uploaded 29 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter Jan 2023-March 2023_0001.pdf · uploaded 29 Dec 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter April 2023 to June 2023_0001.pdf · uploaded 29 Dec 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter June 2023-Sep 2023_0001.pdf · uploaded 29 Dec 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Quarter April 2023-June 2023_0001.pdf · uploaded 29 Dec 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Quarter 1 31032023_0001.pdf · uploaded 20 Jan 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Quarter 2 30062023_0001.pdf · uploaded 20 Jan 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Quarter 3 30092023_0001.pdf · uploaded 20 Jan 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Quarter 4 31122023_0001.pdf · uploaded 20 Jan 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter 1 31032023_0001.pdf · uploaded 20 Jan 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter 2 30062023_0001.pdf · uploaded 20 Jan 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Quarter 3 30092023_0001.pdf · uploaded 20 Jan 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · FOrm 2 Quarter 4 31122023.pdf · uploaded 20 Jan 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Quarter 4 31122023_0001.pdf · uploaded 20 Jan 2024Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P51700048627 · Form 5 from HSMP for 2022-23.pdf · uploaded 11 Mar 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Dipti Skycity March 2024 Signed_0001.pdf · uploaded 20 Apr 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Sky city March 2024 Signed_0001.pdf · uploaded 20 Apr 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Dipti Sky City March 2024 Signed_0001.pdf · uploaded 20 Apr 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Skycity 30062024 Signed_0001.pdf · uploaded 20 Jul 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 SkyCity 30062024 Signed_0001.pdf · uploaded 20 Jul 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 SkyCity 30062024 signed_0001.pdf · uploaded 24 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Skycity Sep 2024 signed_compressed.pdf · uploaded 19 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Skycity Sep 2024 Signed_0001.pdf · uploaded 21 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Skycity Sep 2024 Signed_0001_0001.pdf · uploaded 21 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Skycity Sep 2024 signed_0001.pdf · uploaded 21 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Skycity Signed Dec 2024_0001.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Skycity Signed Dec 2024 New_0001.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Signed Skycity Dec 2024.pdf · uploaded 27 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Sky City March 2025.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Sky City March 2025_compressed.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Form 2 Sky city March 2025.pdf · uploaded 19 Apr 2025Source
  • 1 Other – LegalP51700048627 · Declaration cum Undertaking 25042025.pdf · uploaded 25 Apr 2025Source
  • 2 Other – LegalP51700048627 · Declaration Rationale account change 24042025.pdf · uploaded 25 Apr 2025Source
  • 3 Other – LegalP51700048627 · Format A 24042025.pdf · uploaded 25 Apr 2025Source
  • 4 Other – LegalP51700048627 · Form 3 Opal Bay Revised 25042025.pdf · uploaded 25 Apr 2025Source
  • 5 Other – LegalP51700048627 · Form 3 Sky City March 2025_compressed.pdf · uploaded 25 Apr 2025Source
  • 6 Other – LegalP51700048627 · Declaration cum undertaking Sky City 24042025.pdf · uploaded 25 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P51700048627 · Form B HDFC 09th july 2025.pdf · uploaded 15 Jul 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P51700048627 · Form 1 Skycity June 2025_0001.pdf · uploaded 19 Jul 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P51700048627 · Skycity form 2 June 2025_0001.pdf · uploaded 19 Jul 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P51700048627 · Form 3 Skycity signed revised_0001.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity June 2025_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity Sep 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity Sep 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity Sep 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity Sep 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Skycity Sep 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · form 1 Skycity Dec 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Sky City March 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 1P51700048627 · Form 1 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Skycity Sep 2025 signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Skycity Sep 2025 signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Skycity Sep 2025 signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Skycity Sep 2025 signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Skycity Sep 2025 signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Sky City_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Skycity March 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2P51700048627 · Form 2 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity June 2026_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity signed revised_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity Signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity Signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity Signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity Signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity Signed_0001.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Dipti Sky City Dec 2025.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity March 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3P51700048627 · Form 3 Skycity June 2026_0001.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2025-2026)P51700048627 · Form 2A 2025-26.pdf · uploaded 1 Oct 2026Source
  • Form 5 (FY 2025-2026)P51700048627 · Form 5 Sky city 2025-26.pdf · uploaded 1 Oct 2026Source

Technical

  • DocumentP51700008856 · 2 com.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700008856 · 3.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700008856 · 1.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700008856 · 1.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700008856 · 2 com.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700008856 · 3.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700048627 · Approved Plan All Pages.pdf · uploaded 8 Oct 2022Source
  • DocumentP51700048627 · Approved Plan All Pages.pdf · uploaded 8 Oct 2022Source

Technical (Architect)

  • DocumentP51700008856 · Arch Certific.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700048627 · Form 1 Skycity Sep 2024 Signed_0001.pdf · uploaded 21 Oct 2024Source
  • DocumentP51700048627 · Form 1 Skycity Sep 2024 Signed_0001_0001.pdf · uploaded 21 Oct 2024Source
  • DocumentP51700048627 · Form 1 Skycity Signed Dec 2024_0001.pdf · uploaded 20 Jan 2025Source
  • DocumentP51700048627 · Form 1 Sky City March 2025.pdf · uploaded 19 Apr 2025Source
  • DocumentP51700048627 · Form 1 Skycity June 2025_0001.pdf · uploaded 19 Jul 2025Source
  • DocumentP51700048627 · Form 1 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source

Technical (Engineer)

  • DocumentP51700008856 · Eng Certi.pdf · uploaded 27 Jul 2017Source
  • DocumentP51700048627 · Form 2 Skycity Sep 2024 signed_0001.pdf · uploaded 21 Oct 2024Source
  • DocumentP51700048627 · Form 2 Signed Skycity Dec 2024.pdf · uploaded 27 Jan 2025Source
  • DocumentP51700048627 · Form 2 Sky city March 2025.pdf · uploaded 19 Apr 2025Source
  • DocumentP51700048627 · Skycity form 2 June 2025_0001.pdf · uploaded 19 Jul 2025Source
  • DocumentP51700048627 · Form 2 Dipti Sky City June 2026.pdf · uploaded 30 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals54 3B 54 3D 57 1, Survey no 543b 543d 571 pt at Ambarnath

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
2
Unit types
2BHK, 1BHK, —230 units in all
Address
Survey no 54-3b 54-3d 57-1 ptPIN 400102
Village
Ambarnath (R), Chavindra taluka
Designated bank account
220
Developed in phases
Yes
Also registered as
Dipti SkyCity Building 1 and 3, Dipti Skycity Bldg No. 7

Survey, CTS, gat or plot numbers

54 3B 54 3D 57 1Survey no 543b 543d 571 pt at Ambarnath

Boundaries

North
boundary of ambernath
South
centre for handicapped-p 186p 54-3
East
24 mtr dp road
West
survey no 54-a and b

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking230 units

35 of 230 units booked (15%), as the promoter reported to MahaRERA

2BHK · 42 units1BHK · 56 units— · 132 units
RERABuildingTypeCarpet areaUnitsBooked
P51700008856Building No 12BHK51.32 sq m · 552 sq ft144
P51700008856Building No 12BHK51.9 sq m · 559 sq ft2817
P51700008856Building No 31BHK33.33 sq m · 359 sq ft288
P51700008856Building No 31BHK33.72 sq m · 363 sq ft286
P51700048627Dipti Sky City Building No 7——132—

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals9

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectJitendra Patel Samarthya Engineers K Patel—P51700048627
ArchitectMr Jitendra S Patel Samarthya Engineers—P51700008856
ArchitectPramod Kamble—P51700048627
Chartered accountantAnita Choudhari—P51700048627
Chartered accountantAshish C Halwai—P51700048627
Chartered accountantDixit Dattatray and Associates D Dixit—P51700048627
Chartered accountantMohandas and Co M Shetty—P51700048627
EngineerAtul Kudtarkar and Associates—P51700048627
EngineerManzur Husain Hebballi—P51700048627

Source: MahaRERA project page. Contact details are not shown.