Deedo IDDP-SIN-ZJCACompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 65% of its units are booked.
Osargaon, Sindhudurg 416603 · by Kalpak Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 14 Aug 2017, completion promised 30 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
7 buildings
Open a building to see every flat, floor by floor.
- Devaki3 floors · 8 units13% booked
- Twin bunglow 21-222 floors · 2 units100% booked
- Twin bunglow 25-262 floors · 2 units100% booked
- Twin bunglow 30A-30B2 floors · 2 units100% booked
- Twin Bunglow 31-322 floors · 2 units100% booked
- Twin bunglow 33-342 floors · 2 units100% booked
- Twin bunglow 35-362 floors · 2 units100% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52900006148
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52900006148 | 14 Aug 2017 | 30 Dec 2028 | 30 Apr 2029 | Kalpak Developers | Project page |
Documents103
1 document held by Deedo, 102 filings listed on MahaRERA's project page
Finance
- PAN CardKALPAK PAN CARD.pdf · uploaded 27 Jul 2017Source
Legal
Migrated
- 1 PAN CardKALPAK PAN CARD.pdf · uploaded 27 Jul 2017Source
- 1 Copy of the legal title reportNANDANVAN TITLE SEARCH REPORT.pdf · uploaded 27 Jul 2017Source
- 1 Details of encumbrancesSELF DECLARATION NO ENCUMBRANCES.pdf · uploaded 27 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)APPROVED LAYOUT.pdf · uploaded 27 Jul 2017Source
Show all 103 documentsShow fewer documents
Migrated
- 1 Building Plan Approval (IOD)APPROVED LAYOUT.pdf · uploaded 27 Jul 2017Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 27 Jul 2017Source
- 1 Proforma of Allotment letterNandanvan -Format.pdf · uploaded 27 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2- NANDANVAN.pdf · uploaded 28 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1- NANDANVAN.PDF · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)FORM 3- NANDANVAN.pdf · uploaded 29 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)REVISED SITE PLAN.pdf · uploaded 20 Dec 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 05 Form 1 - 30Jun2021.pdf · uploaded 29 Mar 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 06 Form 1 - 30Sep2021.pdf · uploaded 29 Mar 2023Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 07 Form 1 - 31Dec2021.pdf · uploaded 29 Mar 2023Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 08 Form 1 - 31Mar2022.pdf · uploaded 29 Mar 2023Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 09 Form 1 - 30Jun2022.pdf · uploaded 29 Mar 2023Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 10 Form 1 - 30Sep2022.pdf · uploaded 29 Mar 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Nandanvan 03 Form 2A -31Mar2020.pdf · uploaded 29 Mar 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Nandanvan 04 Form 2A -31Mar2021.pdf · uploaded 29 Mar 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Nandanvan 05 Form 2A -31Mar2022.pdf · uploaded 29 Mar 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)01 Nandanvan Form 2 31032018.pdf · uploaded 1 Apr 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)02 Nandanvan Form 2 31032019.pdf · uploaded 1 Apr 2023Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)03 Nandanvan Form 2 31032020.pdf · uploaded 1 Apr 2023Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)04 Nandanvan Form 2 31032021.pdf · uploaded 1 Apr 2023Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)05 Nandanvan Form 2 30062021.pdf · uploaded 1 Apr 2023Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)06 Nandanvan Form 2 30092021.pdf · uploaded 1 Apr 2023Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)07 Nandanvan Form 2 31122021.pdf · uploaded 1 Apr 2023Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)08 Nandanvan Form 2 31032022.pdf · uploaded 1 Apr 2023Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)09 Nandanvan Form 2 30062022.pdf · uploaded 1 Apr 2023Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)10 Nandanvan Form 2 30092022.pdf · uploaded 1 Apr 2023Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)11 Nandanvan Form 2 31122022.pdf · uploaded 1 Apr 2023Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 01 Form 1 - 31Mar2018.pdf · uploaded 4 Apr 2023Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 02 Form 1 - 31Mar2019.pdf · uploaded 4 Apr 2023Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 03 Form 1 - 31Mar2020.pdf · uploaded 4 Apr 2023Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 04 Form 1 - 31Mar2021.pdf · uploaded 4 Apr 2023Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Nandanvan 11 Form 1 - 31Dec2022.pdf · uploaded 4 Apr 2023Source
- 2 Certificates of CA (Form 3)Nandanvan 01 Form 3 -31Mar2018.pdf · uploaded 19 Apr 2023Source
- 3 Certificates of CA (Form 3)Nandanvan 02 Form 3 -31Mar2019.pdf · uploaded 19 Apr 2023Source
- 4 Certificates of CA (Form 3)Nandanvan 03 Form 3 -31Mar2020.pdf · uploaded 19 Apr 2023Source
- 5 Certificates of CA (Form 3)Nandanvan 04 Form 3 -31Mar2021.pdf · uploaded 19 Apr 2023Source
- 6 Certificates of CA (Form 3)Nandanvan 05 Form 3 -30Jun2021.pdf · uploaded 19 Apr 2023Source
- 7 Certificates of CA (Form 3)Nandanvan 06 Form 3 -30Sep2021.pdf · uploaded 19 Apr 2023Source
- 8 Certificates of CA (Form 3)Nandanvan 07 Form 3 -31Dec2021.pdf · uploaded 19 Apr 2023Source
- 9 Certificates of CA (Form 3)Nandanvan 08 Form 3 -31Mar2022.pdf · uploaded 19 Apr 2023Source
- 10 Certificates of CA (Form 3)Nandanvan 09 Form 3 -30Jun2022.pdf · uploaded 19 Apr 2023Source
- 11 Certificates of CA (Form 3)Nandanvan 10 Form 3 -30Sep2022.pdf · uploaded 19 Apr 2023Source
- 12 Certificates of CA (Form 3)Nandanvan 11 Form 3 -31Dec2022.pdf · uploaded 19 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)01 Nandanvan - Annual Report 17-18.pdf · uploaded 19 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)02 Nandanvan - Annual Report 18-19.pdf · uploaded 19 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)03 Nandanvan - Annual Report 19-20.pdf · uploaded 19 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)04 Nandanvan - Annual Report 20-21.pdf · uploaded 19 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)05 Nandanvan - Annual Report 21-22.pdf · uploaded 20 Apr 2023Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)01 Form 1 Architect - Nandanvan Mar 23.pdf · uploaded 12 Aug 2024Source
- 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)02 Form 1 Architect - Nandanvan June 23.pdf · uploaded 12 Aug 2024Source
- 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)03 Form 1 Architect - Nandanvan Sep 23.pdf · uploaded 12 Aug 2024Source
- 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)04 Form 1 Architect - Nandanvan Dec 23.pdf · uploaded 12 Aug 2024Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)01 Form 2 Engineers - Nandanvan Mar 23.pdf · uploaded 12 Aug 2024Source
- 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)02 Form 2 Engineers - Nandanvan June 23.pdf · uploaded 12 Aug 2024Source
- 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)03 Form 2 Engineers - Nandanvan Sep 23.pdf · uploaded 12 Aug 2024Source
- 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)04 Form 2 Engineers - Nandanvan Dec 23.pdf · uploaded 12 Aug 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Quality Assurance Nandanvan 22-23.pdf · uploaded 12 Aug 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Inventory - Nandanvan.pdf · uploaded 13 Aug 2024Source
- 13 Certificates of CA (Form 3)13 Form 3 CA Certificate - Nandanvan Mar 23.pdf · uploaded 13 Aug 2024Source
- 14 Certificates of CA (Form 3)14 Form 3 CA Certificate - Nandanvan June 23.pdf · uploaded 13 Aug 2024Source
- 15 Certificates of CA (Form 3)15 Form 3 CA Certificate - Nandanvan Sep 23.pdf · uploaded 13 Aug 2024Source
- 16 Certificates of CA (Form 3)16 Form 3 CA Certificate - Nandanvan Dec 23.pdf · uploaded 13 Aug 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Annual Certificate 2023 Nandanvan.pdf · uploaded 13 Aug 2024Source
- Form 1Nandanvan 01 Form 1 - 31Mar2024.pdf · uploaded 17 Jun 2026Source
- Form 2Nandanvan Form 2 01- 31Mar2024.pdf · uploaded 17 Jun 2026Source
- Form 3Form 3 CA Certificate 01 31Mar24 Nandanvan.pdf · uploaded 17 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 01 31Mar2024.pdf · uploaded 17 Jun 2026Source
- Form 1Nandanvan 03 Form 1 - 31Mar2025.pdf · uploaded 17 Jun 2026Source
- Form 2Nandanvan Form 2 03- 31Mar2025.pdf · uploaded 17 Jun 2026Source
- Form 3Form 3 CA Certificate 02 31Mar25 Nandanvan.pdf · uploaded 17 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 01 31Mar2025.pdf · uploaded 17 Jun 2026Source
- Form 1Nandanvan 04 Form 1 - 30June2025.pdf · uploaded 17 Jun 2026Source
- Form 2Nandanvan Form 2 04- 30June2025.pdf · uploaded 17 Jun 2026Source
- Form 3Form 3 CA Certificate 03 30Jun25 Nandanvan.pdf · uploaded 17 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 01 30Jun2025.pdf · uploaded 17 Jun 2026Source
- Form 1Nandanvan 05 Form 1 - 30Sep2025.pdf · uploaded 17 Jun 2026Source
- Form 2Nandanvan Form 2 05- 30Sep2025.pdf · uploaded 17 Jun 2026Source
- Form 3Form 3 CA Certificate 04 30Sep25 Nandanvan.pdf · uploaded 17 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 04 30Sep2025.pdf · uploaded 17 Jun 2026Source
- Form 1Nandanvan 06 Form 1 - 31Dec2025.pdf · uploaded 22 Jun 2026Source
- Form 2Nandanvan Form 2 06- 31Dec2025.pdf · uploaded 22 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 01 31Dec2025.pdf · uploaded 22 Jun 2026Source
- Form 3Form 3 CA Certificate 05 31Dec25 Nandanvan.pdf · uploaded 22 Jun 2026Source
- Form 2A (FY 2024-2025)Form 2A March 2025.pdf · uploaded 22 Jun 2026Source
- Form 2A (FY 2025-2026)Form 2A March 2026.pdf · uploaded 22 Jun 2026Source
- Form 5 (FY 2024-2025)RERA Annual Certificate 2025 Nandanvan1.pdf · uploaded 22 Jun 2026Source
- Form 1Nandanvan 07 Form 1 - 31Mar2026.pdf · uploaded 23 Jun 2026Source
- Form 2Nandanvan Form 2 07- 31Mar2026.pdf · uploaded 23 Jun 2026Source
- Form 3Form 3 CA Certificate 06 31Mar26 Nandanvan.pdf · uploaded 23 Jun 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory 01 31Mar2026.pdf · uploaded 23 Jun 2026Source
Technical
Technical (Architect)
- Document04 Form 1 Architect - Nandanvan Dec 23.pdf · uploaded 12 Aug 2024Source
Technical (Engineer)
- Document04 Form 2 Engineers - Nandanvan Dec 23.pdf · uploaded 12 Aug 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GUT 1668C GUT 1668D
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1RK, 2BHK, Shop 1, Shop 2, 3BHK20 units in all
- Address
- GUT 1668C GUT 1668D, Osargaon, OsargaonPIN 416603
- Village
- Osargaon, Kankavli taluka
- Location
- 16.20655, 73.69996
- Land area for this project
- 3,489 sq m (37,555 sq ft)
- Permissible built-up area
- 4,092 sq m (44,046 sq ft)
- Sanctioned built-up area
- 4,092 sq m (44,046 sq ft)
- Recreational open space
- 1,761 sq m (18,950 sq ft)
- Designated bank account
- 190
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GUT 1668C GUT 1668D
Boundaries
- North
- Plot Gut No 1668e
- South
- Plot Gut No 1688b
- East
- National Highway 66
- West
- Waterpond
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
13 of 20 units booked (65%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Devaki | 1RK | 45 sq m · 484 sq ft | 1 | 0 |
| Devaki | 1RK | 51.09 sq m · 550 sq ft | 1 | 1 |
| Devaki | 2BHK | 108 sq m · 1,163 sq ft | 2 | 0 |
| Devaki | 2BHK | 125 sq m · 1,345 sq ft | 2 | 0 |
| Devaki | Shop 1 | 102 sq m · 1,098 sq ft | 1 | 0 |
| Devaki | Shop 2 | 152 sq m · 1,636 sq ft | 1 | 0 |
| Twin bunglow 21-22 | 3BHK | 127 sq m · 1,367 sq ft | 2 | 2 |
| Twin bunglow 25-26 | 3BHK | 127 sq m · 1,367 sq ft | 2 | 2 |
Show all 12 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Twin bunglow 30A-30B | 3BHK | 139.35 sq m · 1,500 sq ft | 2 | 2 |
| Twin Bunglow 31-32 | 3BHK | 139.35 sq m · 1,500 sq ft | 2 | 2 |
| Twin bunglow 33-34 | 3BHK | 139.35 sq m · 1,500 sq ft | 2 | 2 |
| Twin bunglow 35-36 | 3BHK | 139.35 sq m · 1,500 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals6
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Milind Kandalgaonkar | — |
| Architect | Rupesh Narayan Tawate | — |
| Chartered accountant | Pramod K Patel | — |
| Chartered accountant | Sagar Gajanan Teli | — |
| Engineer | Kapil Namdeo Dalvi | — |
| Engineer | Rupesh N Tawate | — |
Source: MahaRERA project page. Contact details are not shown.