Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 0% of its units are booked.

Kalmath, Sindhudurg 416602 · by Om Sai Builders And Developers

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 42 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 2 May 2025, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52900080170
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P529000801702 May 202531 Dec 202930 Apr 2030Om Sai Builders And DevelopersProject page
Documents48

1 document held by Deedo, 47 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card.pdf · uploaded 12 Mar 2025Source
  • Other – Financedeclaration cum undertaking.pdf · uploaded 26 Mar 2025Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 12 Mar 2025Source
  • Other – LegalLAND PURCHASE.pdf · uploaded 13 Mar 2025Source
  • Other – LegalPARTNERSHIP DEED.pdf · uploaded 13 Mar 2025Source
  • Other – Legalself deceleration of partnership firm.pdf · uploaded 13 Mar 2025Source
  • Declaration Form BFORM B.pdf · uploaded 13 Mar 2025Source
Show all 48 documentsShow fewer documents

Migrated

  • 1 PAN Cardpan card.pdf · uploaded 12 Mar 2025Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 12 Mar 2025Source
  • 1 a Details of encumbrances concerned to Financeincumbrance certificate to finance.pdf · uploaded 12 Mar 2025Source
  • 2 a Details of encumbrances concerned to Financeencumbrance certificate to legal.pdf · uploaded 12 Mar 2025Source
  • 1 b Details of encumbrances concerned to Legalincumbrance certificate to finance.pdf · uploaded 12 Mar 2025Source
  • 2 b Details of encumbrances concerned to Legalencumbrance certificate to legal.pdf · uploaded 12 Mar 2025Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 13 Mar 2025Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 13 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 13 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate (1).pdf · uploaded 13 Mar 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate.pdf · uploaded 13 Mar 2025Source
  • 3 Other – Legalself deceleration of partnership firm.pdf · uploaded 13 Mar 2025Source
  • 1 Other – LegalLAND PURCHASE.pdf · uploaded 13 Mar 2025Source
  • 2 Other – LegalPARTNERSHIP DEED.pdf · uploaded 13 Mar 2025Source
  • 1 CERSAI detailsCersai certificate.pdf · uploaded 13 Mar 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)declaration of bank account.pdf · uploaded 13 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterdeviation to allotment letter.pdf · uploaded 13 Mar 2025Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation model copy of agreement.pdf · uploaded 13 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest in other real estate.pdf · uploaded 13 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)BANK LETTER.pdf · uploaded 13 Mar 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectdisclosure for secured-unsecured finance.pdf · uploaded 13 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM 3 SCAN.pdf · uploaded 26 Mar 2025Source
  • 1 Other – Financedeclaration cum undertaking.pdf · uploaded 26 Mar 2025Source
  • 1 Other – Technicaldeclaration cum undertaking.pdf · uploaded 26 Mar 2025Source
  • 2 Other – TechnicalMAIL PHOTO.pdf · uploaded 27 Mar 2025Source
  • 3 Other – TechnicalLETTER KALMATH.pdf · uploaded 27 Mar 2025Source
  • 1 Proforma of Agreement for saleAgreement to sale.pdf · uploaded 27 Mar 2025Source
  • 1 Copy of Layout Approval (in case of layout)SAI HERITAGE PLAN.pdf · uploaded 29 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentSAI HERITAGE PLAN.pdf · uploaded 29 Mar 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentNAGAR RACHANA.pdf · uploaded 7 Apr 2025Source
  • 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 7 Apr 2025Source
  • 2 Declaration about Commencement CertificateKalmath Grampanchyayat.pdf · uploaded 7 Apr 2025Source
  • 3 Commencement Certificates / NA Order for plotted developmentMAIL SCREENSHOT.pdf · uploaded 22 Apr 2025Source

Technical

  • Other – Technicaldeclaration cum undertaking.pdf · uploaded 26 Mar 2025Source
  • Other – TechnicalMAIL PHOTO.pdf · uploaded 27 Mar 2025Source
  • Other – TechnicalLETTER KALMATH.pdf · uploaded 27 Mar 2025Source
  • DocumentSAI HERITAGE PLAN.pdf · uploaded 29 Mar 2025Source
  • DocumentSAI HERITAGE PLAN.pdf · uploaded 29 Mar 2025Source

Technical (Architect)

  • DocumentArchitect certificate.pdf · uploaded 13 Mar 2025Source

Technical (Engineer)

  • DocumentEngineer certificate (1).pdf · uploaded 13 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 166A/6/A1

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop42 units in all
Address
166a/6/A1, Kalmath, KalmathPIN 416602
Village
kalmath, Kankavli taluka
Land area for this project
841 sq m (9,052 sq ft)
Permissible built-up area
1,509 sq m (16,240 sq ft)
Sanctioned built-up area
1,509 sq m (16,240 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
190
Developed in phases
No

Survey, CTS, gat or plot numbers

166A/6/A1

Land as published on MahaRERA's project page

166A/6/A1

Boundaries

North
City Survey No 104
South
Aachara Kankavli Road
East
Internal Road
West
City Survey No 107

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking42 units

0 of 42 units booked (0%), as the promoter reported to MahaRERA

1BHK · 6 units2BHK · 6 unitsShop · 30 units
TypeCarpet areaUnitsBooked
1BHK49.05 sq m · 528 sq ft30
1BHK50 sq m · 538 sq ft30
2BHK60.77 sq m · 654 sq ft30
2BHK65.9 sq m · 709 sq ft30
Shop11.51 sq m · 124 sq ft200
Shop14.2 sq m · 153 sq ft10
Shop15.43 sq m · 166 sq ft10
Shop15.81 sq m · 170 sq ft10
Show all 12 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop17.04 sq m · 183 sq ft10
Shop17.68 sq m · 190 sq ft40
Shop32.74 sq m · 352 sq ft10
Shop44.27 sq m · 477 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmol Nashte And Associates—
Chartered accountantKpt And Associates LLP—
EngineerNikhil Sanjay Khochare—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology