Skip to content
Promised date passed6 floorsRERA P52900010951

B2, Hapus Homes - Phase 1

Deedo IDDP-SIN-EBBE-B2

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Booked72%13 of 18 · MahaRERA
Completion31 Dec 2017as registered
Units & parking in B2
TypeCarpet areaUnitsBooked
2 BHK54.2 m² (584 sq.ft)1611
2 BHK GARDEN FLAT54.1 m² (582 sq.ft)22
As registered with MahaRERA
RERA registration
P52900010951 · registered 31 Aug 2017
Promised completion
31 Dec 2017
Revised completion
31 Dec 2017
Sanctioned habitable floors
6
Sanctioned floors (incl. basement, stilt, podium)
6
Units declared
0
Homes
0
Shops and offices
0
MahaRERA status
Certificate Signed
Deedo ID
DP-SIN-EBBE-B2
Questions about B2

When is B2 due for completion?

The MahaRERA registration promises 31 Dec 2017.

How many floors does B2 have?

6 sanctioned habitable floors, as registered with MahaRERA.

Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology