Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Parale, Satara 415124 · by Shital Tanaji Ramugade

Delivery1 yr 11 mo past duePromised Dec 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 16 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 29 Sep 2021, completion promised 31 Dec 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52700030938
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5270003093829 Sep 202131 Dec 202431 Dec 2024Shital Tanaji RamugadeProject page
Documents26

1 document held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardshital ramugade pan card.pdf · uploaded 11 Aug 2021Source

Legal

  • Declaration Form BForm-B.pdf · uploaded 3 Sep 2021Source
  • Legal Title reportligal report(1).pdf · uploaded 22 Sep 2021Source

Migrated

  • 1 PAN Cardshital ramugade pan card.pdf · uploaded 11 Aug 2021Source
  • 1 Copy of Layout Approval (in case of layout)PLOT LYOUAT.pdf · uploaded 11 Aug 2021Source
  • 1 Building Plan Approval / NA Order for plotted development2-08-2021 BANDHAKAM PLAN.pdf · uploaded 11 Aug 2021Source
  • 1 Commencement Certificates / NA Order for plotted development2-08-2021- BANDHAKAM PARVANGI.pdf · uploaded 11 Aug 2021Source
Show all 26 documentsShow fewer documents

Migrated

  • 1 Proforma of Allotment lettershital Ramugade RERA Sample.pdf · uploaded 25 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect.pdf · uploaded 2 Sep 2021Source
  • 1 Details of encumbrancesencumbrances.pdf · uploaded 3 Sep 2021Source
  • 1 Declaration in FORM BForm-B.pdf · uploaded 3 Sep 2021Source
  • 1 Declaration about Commencement CertificateDECLARATION.pdf · uploaded 6 Sep 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CER.pdf · uploaded 6 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFCATE NO 3.pdf · uploaded 6 Sep 2021Source
  • 1 Copy of the legal title reportligal report(1).pdf · uploaded 22 Sep 2021Source
  • 2 Proforma of Allotment letterAllotment letter.pdf · uploaded 22 Sep 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT FORM -1-31122021.pdf · uploaded 14 Jan 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S FORM-2-31122021.pdf · uploaded 14 Jan 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM 2A- 1-31122021.pdf · uploaded 14 Jan 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA FORM-3-31122021.pdf · uploaded 14 Jan 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200259371709_For_Asset_Based_Search_03_02_2023_10_25_17_928.pdf · uploaded 21 Jun 2023Source

Technical

  • DocumentPLOT LYOUAT.pdf · uploaded 11 Aug 2021Source
  • Document2-08-2021 BANDHAKAM PLAN.pdf · uploaded 11 Aug 2021Source

Technical (Architect)

  • DocumentARCHITECT FORM -1-31122021.pdf · uploaded 14 Jan 2022Source

Technical (Engineer)

  • DocumentENGINEER'S FORM-2-31122021.pdf · uploaded 14 Jan 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 85/2/3/4/5/K/D PLOT NO5

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK16 units in all
Address
85/2/3/4/5/K/D Plot No-5, Banawadi, Aahear CoPIN 415124
Village
Parale, Karad taluka
Land area for this project
298 sq m (3,210 sq ft)
Permissible built-up area
666 sq m (7,164 sq ft)
Sanctioned built-up area
328 sq m (3,531 sq ft)
Recreational open space
298 sq m (3,210 sq ft)
Designated bank account
116
Developed in phases
No

Survey, CTS, gat or plot numbers

85/2/3/4/5/K/D PLOT NO5

Land as published on MahaRERA's project page

85/2/3/4/5/K/D PLOT NO-5

Boundaries

North
Plot No-6
South
Plot No-4
East
Road
West
Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

0 of 16 units booked (0%), as the promoter reported to MahaRERA

1BHK · 16 units
TypeCarpet areaUnitsBooked
1BHK30.49 sq m · 328 sq ft10
1BHK30.49 sq m · 328 sq ft10
1BHK30.49 sq m · 328 sq ft10
1BHK30.49 sq m · 328 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
Show all 16 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK31.48 sq m · 339 sq ft10
1BHK34.96 sq m · 376 sq ft10
1BHK34.96 sq m · 376 sq ft10
1BHK34.96 sq m · 376 sq ft10
1BHK34.96 sq m · 376 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmol Lokare—
Chartered accountantCa Nikhil Oswal—