RegisteredMahaRERA status: Certificate Signed

PR1320002501254

Rakhi Tower · Solapur (M Corp.), Solapur · Shiva Construction

Promised for 31 Dec 2028 and not extended so far.

2 years and 1 month to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate16 Oct 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1320002501254

Is Rakhi Tower delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2028, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1320002501254.

Who is the promoter?

MahaRERA records Shiva Construction as the promoter of PR1320002501254.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1320002501254.

Answers are generated from the record.

Data through25 Oct 2026, 03:27SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology