RegisteredExtendedMahaRERA status: Certificate Signed

PR1270002400019

Pushp Dwarka · Poyanje, Raigarh · Hari Om Builders And Developers

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate26 Sep 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1270002400019

Is Pushp Dwarka delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1270002400019. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Hari Om Builders And Developers as the promoter of PR1270002400019.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1270002400019.

Answers are generated from the record.

Data through9 Nov 2026, 02:38SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology