Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered

PR1220002602449

Aureon Crest · Nashik · Aureon Constructions

Promised for 31 Mar 2029 and not extended so far.

2 years and 4 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate19 Oct 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PR1220002602449

Is Aureon Crest delayed?

Not so far. MahaRERA records a promised completion of 31 Mar 2029, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PR1220002602449.

Who is the promoter?

MahaRERA records Aureon Constructions as the promoter of PR1220002602449.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PR1220002602449.

Answers are generated from the record.

Data through9 Nov 2026, 02:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology