Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

PP1260002500646

Unnati Vatika · Koregaon Mul, Pune · Unnati Lifespace

Promised for 30 Apr 2027, extended once to 30 Aug 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Apr 2027 to 30 Aug 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate15 Jun 2026View
Registration certificate4 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PP1260002500646

Is Unnati Vatika delayed?

Its completion moved from 30 Apr 2027 to 30 Aug 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for PP1260002500646. The completion date moved from 30 Apr 2027 to 30 Aug 2027.

Who is the promoter?

MahaRERA records Unnati Lifespace as the promoter of PP1260002500646.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PP1260002500646.

Answers are generated from the record.

Data through9 Nov 2026, 02:42SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology