RegisteredMahaRERA status: Certificate Signed
PP1190002601555
Aerocity 1 · Hingna, Nagpur · Vedant Developers
Promised for 30 Jun 2029 and not extended so far.
2 years and 7 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PP1190002601555
Is Aerocity 1 delayed?
Not so far. MahaRERA records a promised completion of 30 Jun 2029, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PP1190002601555.
Who is the promoter?
MahaRERA records Vedant Developers as the promoter of PP1190002601555.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PP1190002601555.