Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredMahaRERA status: Certificate Signed

PP1190002601555

Aerocity 1 · Hingna, Nagpur · Vedant Developers

Promised for 30 Jun 2029 and not extended so far.

2 years and 7 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate14 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PP1190002601555

Is Aerocity 1 delayed?

Not so far. MahaRERA records a promised completion of 30 Jun 2029, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PP1190002601555.

Who is the promoter?

MahaRERA records Vedant Developers as the promoter of PP1190002601555.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PP1190002601555.

Answers are generated from the record.

Data through23 Nov 2026, 01:57SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology