RegisteredExtendedMahaRERA status: Certificate Signed

PM1330002600063

Sai Palace · Thane (M Corp.), Thane · Sai Enterprises

Promised for 25 Aug 2029, extended to 25 Dec 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 25 Aug 2029 to 25 Dec 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate10 Apr 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PM1330002600063

Is Sai Palace delayed?

Its completion moved from 25 Aug 2029 to 25 Dec 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PM1330002600063. The completion date moved from 25 Aug 2029 to 25 Dec 2029.

Who is the promoter?

MahaRERA records Sai Enterprises as the promoter of PM1330002600063.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PM1330002600063.