RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
PM1330002600063
Sai Palace · Thane (M Corp.), Thane · Sai Enterprises
Promised for 25 Aug 2029, extended to 25 Dec 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 25 Aug 2029 to 25 Dec 2029.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PM1330002600063
Is Sai Palace delayed?
Its completion moved from 25 Aug 2029 to 25 Dec 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PM1330002600063. The completion date moved from 25 Aug 2029 to 25 Dec 2029.
Who is the promoter?
MahaRERA records Sai Enterprises as the promoter of PM1330002600063.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PM1330002600063.
Answers are generated from the record.
