Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

PM1260002502537

Sai Savera · Kiwale, Pune · Sai Gajanan Associates

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate10 Sep 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about PM1260002502537

Is Sai Savera delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PM1260002502537. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records Sai Gajanan Associates as the promoter of PM1260002502537.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PM1260002502537.

Answers are generated from the record.