RegisteredExtendedMahaRERA status: Certificate Signed

PM1260002501640

Kumar Prism Tower A · Keshavnagar Mundwa, Pune · Kumar Prism Realty LLP

Promised for 31 Dec 2031, extended to 30 Apr 2032, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2031 to 30 Apr 2032.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate2 Dec 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about PM1260002501640

Is Kumar Prism Tower A delayed?

Its completion moved from 31 Dec 2031 to 30 Apr 2032; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for PM1260002501640. The completion date moved from 31 Dec 2031 to 30 Apr 2032.

Who is the promoter?

MahaRERA records Kumar Prism Realty LLP as the promoter of PM1260002501640.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names PM1260002501640.

Answers are generated from the record.

Data through9 Nov 2026, 02:45SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology