PM1180002600845
Supreme Ellora · Kolekalyan, Mumbai Suburban · Supreme Realtors
Promised for 30 Oct 2028, extended to 28 Feb 2029, which is still ahead.
The revised date is 4 months after the original promise.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Oct 2028 to 28 Feb 2029.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about PM1180002600845
Is Supreme Ellora delayed?
Its completion moved from 30 Oct 2028 to 28 Feb 2029; the revised date has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for PM1180002600845. The completion date moved from 30 Oct 2028 to 28 Feb 2029.
Who is the promoter?
MahaRERA records Supreme Realtors as the promoter of PM1180002600845.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names PM1180002600845.