Supreme Realtors

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Arbuda Darshan Chs Ltd.P51800030268Andheri2021Certificate Signed31 Dec 202331 Dec 2023On date
Shree Shreyas ChslP51800052929Kolekalyan2023Completed1 Jun 2024—On date
Supreme ElloraPM1180002600845Kolekalyan2026Certificate Signed30 Oct 202828 Feb 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Arbuda Darshan Chs Ltd.On date
  • Shree Shreyas ChslOn date
  • Supreme Ellora+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Supreme Ellora (PM1180002600845).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology