Registered1 extensionMahaRERA status: Certificate Signed

P99000077850

Raj Anant H Wing · Palghar · Shree Raj Corporation

Promised for 31 Mar 2025, extended once to 30 Jun 2027, which is still ahead.

The revised date is 2 years and 3 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2025 to 30 Jun 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate7 Nov 2024View
Extension certificate15 May 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000077850

Is Raj Anant H Wing delayed?

Its completion moved from 31 Mar 2025 to 30 Jun 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000077850. The completion date moved from 31 Mar 2025 to 30 Jun 2027.

Who is the promoter?

MahaRERA records Shree Raj Corporation as the promoter of P99000077850.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000077850.