Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P99000033448

Gangotri Heights · Vasaivirar City (M Corp), Palghar · Shree Yogi Builders & Developer

Promised for 31 Dec 2028, extended to 30 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2028 to 30 Apr 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate22 Feb 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000033448

Is Gangotri Heights delayed?

Its completion moved from 31 Dec 2028 to 30 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P99000033448. The completion date moved from 31 Dec 2028 to 30 Apr 2029.

Who is the promoter?

MahaRERA records Shree Yogi Builders & Developer as the promoter of P99000033448.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000033448.

Answers are generated from the record.

Data through3 Nov 2026, 02:10SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology