RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000031744

Amin Complex · Manor, Palghar · Gajarya Associates

Promised for 31 Mar 2022, extended once to 31 Mar 2025 — and that date has passed without the project marked complete on MahaRERA.

4 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2022 to 31 Mar 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Mar 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate8 Nov 2021View
Extension certificate27 Mar 2023View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P99000031744

Is Amin Complex delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2022, revised to 31 Mar 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000031744. The completion date moved from 31 Mar 2022 to 31 Mar 2025.

Who is the promoter?

MahaRERA records Gajarya Associates as the promoter of P99000031744.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000031744.

Answers are generated from the record.

Data through1 Nov 2026, 03:05SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology