Registered1 extensionMahaRERA status: Certificate Signed

P99000012924

Bright Galaxy · Vasaivirar City (M Corp), Palghar · Barkaat Builders

Promised for 14 Dec 2018, extended once to 30 Jun 2027, which is still ahead.

The revised date is 8 years and 6 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 14 Dec 2018 to 30 Jun 2027 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate7 Sep 2017View
Extension certificate9 Mar 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000012924

Is Bright Galaxy delayed?

Its completion moved from 14 Dec 2018 to 30 Jun 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000012924. The completion date moved from 14 Dec 2018 to 30 Jun 2027.

Who is the promoter?

MahaRERA records Barkaat Builders as the promoter of P99000012924.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000012924.

Answers are generated from the record.

Data through3 Nov 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology