RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P99000011081
Galaxy Apartment · Vasaivirar City (M Corp), Palghar · Orchid Construction
Promised for 31 Dec 2018, extended once to 30 Dec 2023 — and that date has passed without the project marked complete on MahaRERA.
7 years and 11 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 31 Dec 2018 to 30 Dec 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Dec 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P99000011081
Is Galaxy Apartment delayed?
Yes. MahaRERA records a promised completion of 31 Dec 2018, revised to 30 Dec 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P99000011081. The completion date moved from 31 Dec 2018 to 30 Dec 2023.
Who is the promoter?
MahaRERA records Orchid Construction as the promoter of P99000011081.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P99000011081.
Answers are generated from the record.