RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P99000007481

Nikhil Tower Building No 2 · Vasaivirar City (M Corp), Palghar · Samarth Builders & Land Developers

Promised for 1 Jun 2019, extended once to 30 Nov 2021 — and that date has passed without the project marked complete on MahaRERA.

7 years and 5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Jun 2019 to 30 Nov 2021 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Nov 2021, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate17 Aug 2017View
Extension certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P99000007481

Is Nikhil Tower Building No 2 delayed?

Yes. MahaRERA records a promised completion of 1 Jun 2019, revised to 30 Nov 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P99000007481. The completion date moved from 1 Jun 2019 to 30 Nov 2021.

Who is the promoter?

MahaRERA records Samarth Builders & Land Developers as the promoter of P99000007481.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P99000007481.

Answers are generated from the record.

Data through7 Nov 2026, 03:12SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology