RegisteredRevised date passedExtendedMahaRERA status: Certificate Signed

P53100055636

Raghvendra Pride · Sangli Miraj Kupwad (M Corp.), Sangli · Raghvendra Construction

Promised for 30 Jun 2026, extended to 30 Oct 2026 — and that date has passed without the project marked complete on MahaRERA.

5 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2026 to 30 Oct 2026.
  • Risk: The latest completion date on record, 30 Oct 2026, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate21 May 2024View

Orders 0

No MahaRERA order or list names this number.

Questions about P53100055636

Is Raghvendra Pride delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2026, revised to 30 Oct 2026, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P53100055636. The completion date moved from 30 Jun 2026 to 30 Oct 2026.

Who is the promoter?

MahaRERA records Raghvendra Construction as the promoter of P53100055636.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100055636.

Answers are generated from the record.

Data through3 Nov 2026, 02:20SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology