RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P53100047610

Varad Ekdant · Sangli Miraj Kupwad (M Corp.), Sangli · Nakshtra Infra

Promised for 31 Mar 2024, extended once to 1 Dec 2024 — and that date has passed without the project marked complete on MahaRERA.

2 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2024 to 1 Dec 2024 (1 extension certificate on record).
  • Risk: The latest completion date on record, 1 Dec 2024, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate14 Nov 2022View
Extension certificate21 May 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P53100047610

Is Varad Ekdant delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2024, revised to 1 Dec 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P53100047610. The completion date moved from 31 Mar 2024 to 1 Dec 2024.

Who is the promoter?

MahaRERA records Nakshtra Infra as the promoter of P53100047610.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100047610.

Answers are generated from the record.

Data through9 Nov 2026, 02:24SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology