Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P53100030141

Indoshiva Tower · Sangli Miraj Kupwad (M Corp.), Sangli · Indoshiva Construction

Promised for 31 Dec 2022, extended once to 31 Aug 2023 — and that date has passed without the project marked complete on MahaRERA.

3 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2022 to 31 Aug 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Aug 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate31 Jul 2021View
Extension certificate28 Apr 2023View

Orders 0

No MahaRERA order or list names this number.

Questions about P53100030141

Is Indoshiva Tower delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2022, revised to 31 Aug 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P53100030141. The completion date moved from 31 Dec 2022 to 31 Aug 2023.

Who is the promoter?

MahaRERA records Indoshiva Construction as the promoter of P53100030141.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100030141.

Answers are generated from the record.

Data through31 Oct 2026, 02:44SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology