Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P53100017830

Arwade Altia · Sangli Miraj Kupwad (M Corp.), Sangli · Mrk Infracon

Promised for 30 Jun 2021, extended once to 30 Dec 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2021 to 30 Dec 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Dec 2022, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 May 2020View
Extension certificate29 Apr 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P53100017830

Is Arwade Altia delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2021, revised to 30 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P53100017830. The completion date moved from 30 Jun 2021 to 30 Dec 2022.

Who is the promoter?

MahaRERA records Mrk Infracon as the promoter of P53100017830.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53100017830.

Answers are generated from the record.

Data through1 Nov 2026, 02:32SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology