P53100003570
Mvk Market · Sangli Miraj Kupwad (M Corp.), Sangli · Maruti Vitthal Kulkarni
Promised for 15 Jan 2019, extended once to 15 Jan 2020 — and that date has passed without the project marked complete on MahaRERA.
7 years and 10 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 15 Jan 2019 to 15 Jan 2020 (1 extension certificate on record).
- !Risk: The latest completion date on record, 15 Jan 2020, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P53100003570
Is Mvk Market delayed?
Yes. MahaRERA records a promised completion of 15 Jan 2019, revised to 15 Jan 2020, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P53100003570. The completion date moved from 15 Jan 2019 to 15 Jan 2020.
Who is the promoter?
MahaRERA records Maruti Vitthal Kulkarni as the promoter of P53100003570.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P53100003570.