RegisteredExtendedMahaRERA status: Certificate Signed

P53000051221

Alankruti Residency · Kolhapur (M Corp.), Kolhapur · Shree Developers

Promised for 31 May 2029, extended to 30 Sep 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 May 2029 to 30 Sep 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate12 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P53000051221

Is Alankruti Residency delayed?

Its completion moved from 31 May 2029 to 30 Sep 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P53000051221. The completion date moved from 31 May 2029 to 30 Sep 2029.

Who is the promoter?

MahaRERA records Shree Developers as the promoter of P53000051221.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P53000051221.