Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P53000017522
Meerabhakti Residency Wing B · Kolhapur (M Corp.), Kolhapur · Shp Properties Private Limited
Promised for 30 Oct 2022, extended once to 30 Oct 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 30 Oct 2022 to 30 Oct 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 30 Oct 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 2
Orders 0
No MahaRERA order or list names this number.
Questions about P53000017522
Is Meerabhakti Residency Wing B delayed?
Yes. MahaRERA records a promised completion of 30 Oct 2022, revised to 30 Oct 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P53000017522. The completion date moved from 30 Oct 2022 to 30 Oct 2023.
Who is the promoter?
MahaRERA records Shp Properties Private Limited as the promoter of P53000017522.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P53000017522.