Shp Properties Private Limited

Deedo IDDD-GXS8

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 48 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay48 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

1 registration of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Meera Bhakti ResidencyP53000000915Kolhapur (M Corp.)Certificate Signed20 Oct 201820 Oct 2018On date
Meerabhakti Residency Wing BP53000017522Kolhapur (M Corp.)Certificate Signed30 Oct 202230 Oct 2023+48 mo*
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology