Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52700047259

Rajkamal Complex · Koregaon, Satara · Sanjay Vinayak Jadhav

Promised for 30 Apr 2024, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

2 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Apr 2024 to 31 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate15 Oct 2022View
Extension certificate22 Jul 2024View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52700047259

Is Rajkamal Complex delayed?

Yes. MahaRERA records a promised completion of 30 Apr 2024, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52700047259. The completion date moved from 30 Apr 2024 to 31 Dec 2025.

Who is the promoter?

MahaRERA records Sanjay Vinayak Jadhav as the promoter of P52700047259.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52700047259.

Answers are generated from the record.

Data through4 Nov 2026, 03:28SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology