RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52700010285

Sky Villas · Patan (Ct), Satara · Agreen Infrastructure Pvt Ltd

Promised for 31 Jan 2021, extended once to 31 Jul 2023 — and that date has passed without the project marked complete on MahaRERA.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Jan 2021 to 31 Jul 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate18 May 2020View
Extension certificate8 Sep 2021View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52700010285

Is Sky Villas delayed?

Yes. MahaRERA records a promised completion of 31 Jan 2021, revised to 31 Jul 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52700010285. The completion date moved from 31 Jan 2021 to 31 Jul 2023.

Who is the promoter?

MahaRERA records Agreen Infrastructure Pvt Ltd as the promoter of P52700010285.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52700010285.

Answers are generated from the record.

Data through1 Nov 2026, 02:00SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology