RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52700009921

Sankalp Heights · Phaltan (M Cl), Satara · Sankalp Developers

Promised for 31 Aug 2018 — that date has passed and MahaRERA does not mark the project complete.

8 years and 3 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Aug 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate22 Aug 2017View

Orders 0

No MahaRERA order or list names this number.

Questions about P52700009921

Is Sankalp Heights delayed?

Yes. MahaRERA records a promised completion of 31 Aug 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52700009921.

Who is the promoter?

MahaRERA records Sankalp Developers as the promoter of P52700009921.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52700009921.

Answers are generated from the record.

Data through9 Nov 2026, 01:48SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology