P52700001674

Samruddhi Appartment · Pirwadi, Satara · Sujeet Manikrao Jagdhane

Promised for 30 Mar 2022, extended once to 30 Mar 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 8 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2022 to 30 Mar 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Mar 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 3

Registration certificate9 Sep 2021View
Extension certificate27 Jun 2022View
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P52700001674

Is Samruddhi Appartment delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2022, revised to 30 Mar 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52700001674. The completion date moved from 30 Mar 2022 to 30 Mar 2023.

Who is the promoter?

MahaRERA records Sujeet Manikrao Jagdhane as the promoter of P52700001674.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52700001674.

Answers are generated from the record.

Data through9 Nov 2026, 01:43SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology