Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P52400017486

736 EWS Ts And 256 MIG Ts At Plot No R-1 Additional MIDC Latur · Latur · Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada)

Promised for 30 Dec 2022 — that date has passed and MahaRERA does not mark the project complete.

3 years and 11 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2022, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate9 Sep 2021View

Orders 0

No MahaRERA order or list names this number.

Questions about P52400017486

Is 736 EWS Ts And 256 MIG Ts At Plot No R-1 Additional MIDC Latur delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P52400017486.

Who is the promoter?

MahaRERA records Aurangabad Housing And Area Development Board ( A Regional Unit Of Mhada) as the promoter of P52400017486.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52400017486.

Answers are generated from the record.

Data through23 Nov 2026, 01:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology