RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P52200047678
Kadampatil Plaza · Kopargaon (R), Ahmednagar · Bhanudas Janardhan Gaikwad
Promised for 15 Jun 2026, extended to 15 Oct 2026 — and that date has passed without the project marked complete on MahaRERA.
5 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 15 Jun 2026 to 15 Oct 2026.
- !Risk: The latest completion date on record, 15 Oct 2026, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 1
Orders 0
No MahaRERA order or list names this number.
Questions about P52200047678
Is Kadampatil Plaza delayed?
Yes. MahaRERA records a promised completion of 15 Jun 2026, revised to 15 Oct 2026, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 0 extension certificates for P52200047678. The completion date moved from 15 Jun 2026 to 15 Oct 2026.
Who is the promoter?
MahaRERA records Bhanudas Janardhan Gaikwad as the promoter of P52200047678.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P52200047678.
Answers are generated from the record.
