RegisteredExtendedMahaRERA status: Certificate Signed

P52100080431

Emerald Grove · Nere, Pune · Omkara Developers

Promised for 29 Dec 2028, extended to 29 Apr 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 29 Dec 2028 to 29 Apr 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate24 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100080431

Is Emerald Grove delayed?

Its completion moved from 29 Dec 2028 to 29 Apr 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100080431. The completion date moved from 29 Dec 2028 to 29 Apr 2029.

Who is the promoter?

MahaRERA records Omkara Developers as the promoter of P52100080431.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100080431.

Answers are generated from the record.