P52100055278

Casalino Towers Phase 3 · Ouatade Handewadi, Pune · Sai Siddhi Promoters And Builders

Promised for 1 Oct 2026, extended to 1 Feb 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 1 Oct 2026 to 1 Feb 2027.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate20 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100055278

Is Casalino Towers Phase 3 delayed?

Its completion moved from 1 Oct 2026 to 1 Feb 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100055278. The completion date moved from 1 Oct 2026 to 1 Feb 2027.

Who is the promoter?

MahaRERA records Sai Siddhi Promoters And Builders as the promoter of P52100055278.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100055278.

Answers are generated from the record.

Data through4 Nov 2026, 02:01SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology