Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52100055046

Venkatesh Anandmayi · Ambegaon Bk, Pune · Shree Venkatesh Enterprises

Promised for 30 Sep 2027, extended once to 30 Jan 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Sep 2027 to 30 Jan 2028 (1 extension certificate on record).
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate19 Aug 2026View
Registration certificate21 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100055046

Is Venkatesh Anandmayi delayed?

Its completion moved from 30 Sep 2027 to 30 Jan 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100055046. The completion date moved from 30 Sep 2027 to 30 Jan 2028.

Who is the promoter?

MahaRERA records Shree Venkatesh Enterprises as the promoter of P52100055046.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100055046.

Answers are generated from the record.

Data through9 Nov 2026, 02:32SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology