Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

Registered1 extensionMahaRERA status: Certificate Signed

P52100054345

Platinum Marvelle · Balewadi, Pune · Platinum Buildcon Private Limited

Promised for 31 Dec 2028 and not extended so far.

2 years and 2 months to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Deedo holds 1 extension certificate for this registration.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Extension certificate20 Aug 2026View
Registration certificate24 Aug 2026View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100054345

Is Platinum Marvelle delayed?

Not so far. MahaRERA records a promised completion of 31 Dec 2028, which has not passed yet.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100054345.

Who is the promoter?

MahaRERA records Platinum Buildcon Private Limited as the promoter of P52100054345.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100054345.

Answers are generated from the record.

Data through29 Oct 2026, 02:34SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology