Skip to content
Company or firm · first RERA registration 2024

Platinum Buildcon Private Limited

Deedo IDDD-1TDV

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
Flats sold, all time36registered sale deeds
Regulatory cases0none on record

No registration has run past its RERA date

Months late against the original RERA promise, per registration

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Platinum MarvelleP52100054345BalewadiCertificate Signed31 Dec 202831 Dec 2028On date