RegisteredExtendedMahaRERA status: Certificate Signed

P52100053897

Westmark · Pimpale Gurav, Pune · Aceprime Skyscraper Llp

Promised for 30 Nov 2028, extended to 30 Mar 2029, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Nov 2028 to 30 Mar 2029.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 1

Registration certificate24 Jan 2025View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100053897

Is Westmark delayed?

Its completion moved from 30 Nov 2028 to 30 Mar 2029; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P52100053897. The completion date moved from 30 Nov 2028 to 30 Mar 2029.

Who is the promoter?

MahaRERA records Aceprime Skyscraper Llp as the promoter of P52100053897.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100053897.